Uzbekistan, Kyrgyzstan, China: Financing contract signed for the CKU Railway

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
Transport & logisticsCentral Asia (regional)1 Source

This summary was written by an AI.

Published · last updated · 27 Jan 2026

The CKU Railway Company LLC signed a $4.7 billion loan agreement in December 2025 to finance the China-Kyrgyzstan-Uzbekistan (CKU) railway project. The People's Republic of China provides over half the funding as a 35-year loan. The project aims to reduce transit times between China and Europe and strengthen Central Asia's role as a transit hub.

Financing Completion and Stakeholders

The CKU Railway Company LLC, a joint venture of the People's Republic of China, Kyrgyzstan, and Uzbekistan, along with a syndicate of Chinese banks, signed a loan agreement on December 16, 2025, in Bishkek. The total project volume is $4.7 billion. The People's Republic of China provides $2.3 billion as a 35-year loan, accounting for approximately half of the project costs. The remaining funds are contributed by the three countries, with China providing 51 percent and Kyrgyzstan and Uzbekistan each contributing 24.5 percent.

Route and Technical Specifications

The railway line starts in Kashgar (China), passes through the Torugart Pass into Kyrgyzstan, and ends in Andijan (Uzbekistan). The total length is 530 kilometers, with 213 kilometers in China, 260 kilometers in Kyrgyzstan, and 50 kilometers in Uzbekistan. The project includes the construction of 50 bridges and 29 tunnels, which account for 40 percent of the route. The construction period is estimated at six years.

Gauges and Transshipment

Two sections with different track gauges are being built. The first section from the Chinese border to the Makmal station in Kyrgyzstan has a gauge of 1435 mm (Chinese standard) and is 165.5 kilometers long. The second section from Makmal to Jalal-Abad in Kyrgyzstan has a gauge of 1520 mm and is 146.2 kilometers long. Freight transshipment and train reorganization due to gauge differences will take place at Makmal station.

Capacity and Geopolitical Context

The CKU railway is expected to transport up to 15 million tons of cargo annually and reduce delivery times from China to Europe by seven days. The project is part of China's Belt and Road Initiative and aims to create a direct connection between China, Central Asia, and Europe without crossing Russian territory. This diversifies Eurasian trade routes and reduces dependence on transit routes through Russia and Kazakhstan.

History and Political Statements

The project was conceived in the 1990s but stalled for decades due to financial and geopolitical hurdles. An agreement on financing and construction start was signed in June 2024, and the official inauguration took place in Jalal-Abad in December 2024. Kyrgyzstan's Deputy Chairman of the Cabinet of Ministers, Bakyt Torobayev, emphasized the joint venture's readiness to implement international-level projects during the signing ceremony.

Project: China-Kyrgyzstan-Uzbekistan Railway · Central Asia (regional) · Under construction · $4.7 bn

Key facts

  • Financing volume: $4.7 billion
  • Loan from PRC: $2.3 billion (35-year term)
  • Total length: 530 kilometers (China 213 km, Kyrgyzstan 260 km, Uzbekistan 50 km)
  • Construction time: estimated six years
  • Capacity: up to 15 million tons of cargo annually
  • Time saving: seven days shorter delivery times to Europe
  • Signing date: December 16, 2025, in Bishkek

All sources (1)

  1. China–Kyrgyzstan–Uzbekistan Railway Financing Loan SignedThe Jamestown Foundation · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn