Active construction has been underway since July 2025 on the China-Kyrgyzstan-Uzbekistan (CKU) Railway. The 530 km route connects Kashgar to Andijan, traversing mountainous terrain in Kyrgyzstan. A joint venture with a Chinese majority stake is managing the project.
Construction Progress and Infrastructure
Active construction has been underway on the Kyrgyz section since July 2025. Earthworks and roadbed formation have begun in some sections. To support the construction site, 192.323 km of temporary roads have been built, four transformer substations installed, 2,095 utility poles erected, and 259 km of power lines strung. Approximately 2,000 Kyrgyz citizens are currently involved in the construction out of a total workforce of 5,000 workers.
Technical Specifications and Route
The final plan outlines a 530 km route, with about 304 km passing through Kyrgyzstan’s Tian Shan mountains. The line connects Kashgar in China to Andijan in Uzbekistan via Torugart, Makmal, and Jalal-Abad. The project features 50 bridges and 29 tunnels with a total length of 104.83 km. Excavation is ongoing in all tunnels, including eight longer than 5 km. Three major tunnels – Naryn No. 1, Kosh-Dobo, and Fergana – are each over 12 km long.
Capacity and Timeline
Based on conservative estimates from the feasibility study, initial freight volume is expected to be between 5 and 8 million tonnes annually, increasing to 13-15 million tonnes long-term. Hikmatulla Rakhmetov, head of Uzbekistan’s state railway company Temir Yullari, stated in November 2025 that completion could be two years ahead of the planned 2030 deadline. Officials aim to have 5 percent of the CKU built by the end of 2026.
Gauge and Transshipment
A compromise on track gauge was reached: from Torugart to Makmal (160 km), a gauge of 1,435 mm will be used. At Makmal, a transshipment station marks the change to 1,520 mm gauge for the section towards Jalal-Abad (145 km). A wheelset exchange facility will be established at Makmal station to handle freight transfer and gauge changes between the two standards.
Financing and Project Company
A joint project company (JPC) was established in Kyrgyzstan under local law. China holds 51 percent, while Kyrgyzstan and Uzbekistan each hold 24.5 percent. The Kyrgyz section is valued at $4.7 billion. China provides a loan of $2.35 billion. Kyrgyzstan contributes approximately $700 million, half from the state budget and the remainder as a $305 million loan with a 25-year term from China.
Challenges: Environment and Resettlement
Beyond technical hurdles, environmental and social challenges persist. The Kyrgyz environmental agency has fined contractors for violations. Along the route, 214 houses must be demolished (191 in Jalal-Abad region, the rest in Naryn). Compensation payments are underway, but not all affected parties agree with the valuations. Public meetings are ongoing to address land rights and compensation issues.
Project: China-Kyrgyzstan-Uzbekistan Railway · Central Asia (regional) · Under construction · $4.7 bn
Key facts
- Active construction start: July 2025
- Total CKU route length: 530 km
- Tunnel length: 104.83 km
- Project volume (Kyrgyz section): $4.7 billion
- Chinese loan: $2.35 billion
- Planned completion: 2030 (possibly 2028)
- China's share in JPC: 51 percent
All sources (1)
- Progress on the China-Kyrgyzstan-Uzbekistan Railway, Some Challenges RemainThe Diplomat – Asia-Pacific Current Affairs Magazine · · EN