Uzbekistan: Construction Start and Financing of the China–Kyrgyzstan–Uzbekistan Railway Corridor

Investors, volumes and stages of the region's major projects – for European suppliers

· 10 Sources

Scroll
Transport & logisticsCentral Asia (regional)10 Sources

Published · last updated · 16 Jun 2026 – 7 Jul 2026

Construction of the strategic railway corridor connecting China, Kyrgyzstan, and Uzbekistan began in December 2024. In June 2026, Kyrgyzstan approved a preferential loan from the Export-Import Bank of China of approximately $305 million to finance its share. The total project cost is estimated at $4.7 billion.

Project Status and Timeline

Construction of the China–Kyrgyzstan–Uzbekistan (CKU) railway corridor officially began on December 27, 2024, in the Jalal-Abad region of Kyrgyzstan. While the initial completion target was 2030, officials now aim for completion by 2028–2029. The total route length is approximately 523 to 530 kilometers, with more than 304 kilometers located within Kyrgyzstan. The Kyrgyz section is technically challenging, featuring 50 bridges and 29 tunnels totaling about 120 kilometers, representing roughly 40 percent of the route in the country.

Financing and Ownership Structure

The estimated total cost of the project is $4.7 billion. Financing is structured through a joint venture where China holds 51 percent, and Kyrgyzstan and Uzbekistan each hold 24.5 percent. China provides $2.3 billion as a loan. Kyrgyzstan finances its share of approximately $609 million, half from the state budget and half through a preferential loan from the Export-Import Bank of China amounting to 2.075 billion yuan (approx. $305 million). The loan has a 25-year term with a five-year grace period and an annual interest rate of 1.5 percent.

Logistical Significance and Capacities

The new connection aims to shorten the trade route between China and Europe by approximately 1,000 kilometers and establish a direct rail link between Central Asia and China, bypassing the existing route through Kazakhstan. Forecasts indicate an annual freight capacity of 15 million tons by 2032, rising to 20 million tons by 2040. The Eurasian Development Bank ranks the project among the ten largest transport infrastructure projects in Central Asia, expecting a fivefold increase in transit traffic by 2030.

Supporting Infrastructure in Uzbekistan

Parallel to the main corridor, three logistics centers are being built in the Tashkent region with a total investment volume of $900 million. One center with $100 million investment is located in the Angren and Achangaran districts, another with $300 million in the Yangiabad district in cooperation with Kazakh entrepreneurs, and a third with $500 million foreign investment in the Qibray district near the Kazakh border. These centers are expected to create at least 7,000 jobs and handle transit traffic once the railway becomes operational.

Regulatory and Social Aspects

In Kyrgyzstan, 214 residential houses were demolished for the construction. While 90 percent of owners have received compensation, disputes remain regarding the compensation amount for two owners. Additionally, the use of the Kyrgyz language on construction site signage was emphasized to comply with legal requirements. The cooperation among the three riparian states also includes harmonizing technical standards and customs procedures.

Project: China-Kyrgyzstan-Uzbekistan Railway · Central Asia (regional) · Under construction · $4.7 bn

Key facts

  • Construction start: December 27, 2024, in Kyrgyzstan
  • Estimated total cost: $4.7 billion
  • Total length: approx. 523–530 kilometers
  • Kyrgyz section: >304 kilometers with 29 tunnels
  • Kyrgyz financing: $305 million loan (Eximbank China)
  • Planned completion: 2028–2029
  • Shares: China 51%, Kyrgyzstan 24.5%, Uzbekistan 24.5%

All sources (10)

  1. Кыргызстан привлечет почти $307 млн на строительство железной дороги Китай – Кыргызстан – УзбекистанАкчабар · · RU
  2. Два владельца не согласны с размером компенсации за снос домов ради железной дорогиКактус.медиа · · RU
  3. Коридор Китай — Кыргызстан — Узбекистан могут открыть к 2028 годуUzDaily · · RU
  4. Cосед Казахстана займет у Китая $304 млн на железнодорожный мегапроектInbusiness.kz · · RU
  5. На стройке железной дороги КНР — КР — РУз призвали делать надписи на кыргызском24.KG · · RU
  6. Kyrgyzstan Approves Chinese Loan for CKU RailwayThe Times Of Central Asia · · EN
  7. Акунбеков: Строительство железной дороги Китай — КР — РУз завершат в срокEconomist.kg · · RU
  8. Три логистических центра на $900 млн строятся в Ташкентской области — хокимГазета.uz · · RU
  9. President launches work on Kyrgyz railway projectRailway Gazette International · · EN
  10. Kyrgyzstan launches a new strategic railway line in the eastern part of the countryRailway PRO · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn