Uzbekistan/Kyrgyzstan: Construction of China-Kyrgyzstan-Uzbekistan Railway Advances

Investors, volumes and stages of the region's major projects – for European suppliers

· 12 Sources

Scroll
Transport & logisticsCentral Asia (regional)12 Sources

Published · last updated · 30 Jul 2026 – 28 Aug 2026

Construction of the 530 km railway link between China, Kyrgyzstan, and Uzbekistan has entered the active phase. The project volume is $4.7 billion, financed by a consortium of Chinese banks. Commissioning is expected by the end of 2030.

Construction Start and Financing

Construction of the China-Kyrgyzstan-Uzbekistan (CKU) railway officially began on December 27, 2024. The total project volume is estimated at $4.7 billion. Financing is provided via a loan from Chinese banks amounting to $2.3 billion with a 35-year term. Shareholding in the CKU Railway Company LLC joint venture is distributed as 51 percent for China, and 24.5 percent each for Kyrgyzstan and Uzbekistan.

Route and Technical Specifications

The line connects Kashgar in China's Xinjiang province with Andijan in Uzbekistan via Kyrgyzstan. The total length is 530 to 532.53 kilometers, with approximately 312 to 304 kilometers on Kyrgyz territory. Due to gauge differences (1,435 mm in China, 1,520 mm in Central Asia), the railway is built in two sections. A 165.5 km section from the Chinese border to Makmal station uses Chinese gauge, while the section from Makmal to Jalal-Abad uses Soviet gauge. Transshipment occurs at Makmal.

Construction Scope and Timeline

The engineering challenge is significant: 40 percent of the route consists of 29 tunnels and 50 bridges. While originally estimated at six years, current indications suggest the project will be completed one year ahead of schedule, by the end of 2030. More than 10,000 specialists and over 7,000 units of heavy machinery are currently deployed on site.

Logistical Capacity and Geopolitical Context

The projected annual transport capacity is up to 15 million tons. The line aims to reduce delivery times from China to Europe and the Middle East by seven to eight days and shorten the route by approximately 900 kilometers compared to northern routes via Kazakhstan and Russia. It serves as an alternative to the Middle Corridor and aims to reduce dependence on Russian transit routes.

Economic Impact and Industrial Development

Beyond transit, the line is intended to stimulate industrial development in the Fergana Valley and Kyrgyzstan. A major transshipment hub with logistics and industrial zones is being built in Makmal. Uzbekistan and Kyrgyzstan plan special economic zones along the route. Bilateral trade between Uzbekistan and Kyrgyzstan rose to $1.2 billion in 2025, with a target of $2 billion.

Project: China-Kyrgyzstan-Uzbekistan Railway · Central Asia (regional) · Under construction · $4.7 bn

Key facts

  • Total length: 530–532.53 km
  • Project volume: $4.7 billion
  • Financing: $2.3 billion loan from Chinese banks
  • Construction start: December 27, 2024
  • Planned completion: End of 2030
  • Annual capacity: up to 15 million tons
  • Shares: China 51%, Kyrgyzstan 24.5%, Uzbekistan 24.5%

All sources (19)

  1. «Стройка века, которая совершенно поменяет геополитику». Шавкат Мирзиёев — о железной дороге Китай-Кыргызстан-УзбекистанГазета.uz · · RU
  2. Construction of China–Kyrgyzstan–Uzbekistan Railway ContinuesUzDaily.uz · · EN
  3. Строительство железной дороги КНР – Кыргызстан – Узбекистан продолжаетсяUzDaily · · RU
  4. Строительство магистрали Китай – Кыргызстан – Узбекистан. На каком этапе находится проект почти за $5 миллиардов. ВидеоPodrobno.uz · · RU
  5. China–Kyrgyzstan–Uzbekistan Railway May Be Completed Ahead of ScheduleUzDaily · · EN
  6. Как железная дорога Китай–Кыргызстан–Узбекистан трансформирует экономическую карту континентаDunyo · · RU
  7. Железную дорогу Китай — КР — РУз могут достроить на год раньшеEconomist.kg · · RU
  8. The Restructuring Of China's Geographic Pathways In Central Asia - Analysiseurasiareview.com · · EN
  9. Китай отказался начинать железную дорогу через Кыргызстан в Узбекистан без согласия России — ЖапаровГазета.uz · · RU
  10. Садыр Жапаров рассказал, зачем встречался с Путиным перед началом строительства железной дороги Китай—КыргызстTazabek.KG · · RU
  11. Железную дорогу до Макмала могут достроить к 2032 годуEconomist.kg · · RU
  12. «Я ездил к Путину за согласием на строительство Китайско-кыргызско-узбекской железной дороги» — ЖапаровKun.uz · · RU
  13. Construction of the China–Kyrgyzstan–Uzbekistan Railway in the focus of Chinese Media attentionDunyo · · EN
  14. Строительство железной дороги Китай–Кыргызстан–Узбекистан в фокусе внимания СМИ КНРDunyo · · RU
  15. Kyrgyzstan seeks $1bn to get rail link ready for CKU openingRailFreight.com · · EN
  16. 26 тоннелей и 40 мостов: как продвигается строительство железной дороги ККУВечерний Бишкек · · RU
  17. Станцию железной дороги КНР - КР - РУз в Манасе завершат к концу 2027 годаВечерний Бишкек · · RU
  18. China–Kyrgyzstan–Uzbekistan Railway Construction Progresses Ahead of ScheduleUzDaily · · EN
  19. Iron Silk Road: Understanding the China–Kyrgyzstan–Uzbekistan RailwayThe Diplomatic Insight · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn