The China-Kyrgyzstan-Uzbekistan (CKU) railway is in the active construction phase, with commissioning planned for 2030. A joint venture with Chinese majority ownership finances the project, with China providing a loan of $2.3 billion. The total route length is 533 kilometers, of which 305 kilometers run through Kyrgyzstan.
Progress and Timeline
Construction of the CKU railway has entered the active phase following the completion of main design documents. Technical documentation is currently being refined and approved. Earthworks, tunneling, and bridge construction are underway, with over 3.5 million cubic meters of excavation already moved. President Sadyr Japarov called the groundbreaking in December 2024 a historic event and set the completion target for 2030.
Financing and Structure
A joint venture was established for the construction, with China holding a 51 percent majority. The remaining shares are divided between Kyrgyzstan and Uzbekistan. China provides a loan of $2.3 billion, of which $1.1 billion is considered an equity contribution. Kyrgyzstan and Uzbekistan each contribute $573 million to the financing. The route connects Kashgar to Andijan and is expected to reduce cargo delivery times by about one week.
Technical Specifications
A key technical challenge is the difference in track gauge: China uses standard gauge of 1,435 millimeters, while Kyrgyzstan and Uzbekistan use broad gauge of 1,520 millimeters. As a compromise, part of the railway in Kyrgyzstan will be built to the Chinese standard, with a transshipment hub to be created. In Kyrgyzstan, the construction of 50 bridges and 29 tunnels is planned, with 90 percent of the Kyrgyz segment running through the mountainous Naryn region.
Economic Prospects
Kyrgyzstan expects revenues of up to $300 million annually from transit and the expansion of logistics infrastructure. Deputy Prime Minister Edil Baisalov emphasized that the project should promote not only transit but also raw material processing and the export of agricultural products. Uzbekistan sees the need to position itself as a logistics hub to avoid functioning merely as an endpoint of a Chinese route.
Project: China-Kyrgyzstan-Uzbekistan Railway · Central Asia (regional) · Under construction · $4.7 bn
Key facts
- Planned commissioning: 2030
- Total route length: 533 km
- Route in Kyrgyzstan: 305 km
- Chinese loan: $2.3 billion
- Kyrgyzstan contribution: $573 million
- Uzbekistan contribution: $573 million
- Active workers: >5,000
- Machinery deployed: >5,600
All sources (5)
- Железную дорогу Китай — Кыргызстан — Узбекистан планируют запустить в 2030 году24.KG · · RU
- The Politics of the China-Kyrgyzstan-Uzbekistan RailwayThe Diplomat – Asia-Pacific Current Affairs Magazine · · EN
- Как продвигается строительство железной дороги Китай - Кыргызстан - УзбекистанКактус.медиа · · RU
- Более 5 тысяч человек задействованы на стройке железной дороги КНР–КР–РУзopen.kg · · RU
- China-Kyrgyzstan-Uzbekistan Railway Enters Active Construction PhaseThe Times Of Central Asia · · EN