Construction of the China-Kyrgyzstan-Uzbekistan Railway (CKU) remains stalled due to unresolved financing models. Beijing, Bishkek, and Tashkent have not yet agreed on cost distribution, leading to delays. The Kyrgyz side faces particular challenges in securing capital.
Unresolved Financing Issues
Construction of the China-Kyrgyzstan-Uzbekistan Railway (CKU) continues to be delayed as China, Kyrgyzstan, and Uzbekistan have not reached an agreement on the financing structure. Gennady Bessonov, Secretary-General of the International Coordinating Council for Trans-Eurasian Transport, stated in September that the countries have not yet reached a mutual agreement on the distribution of financing responsibilities. This disagreement could prolong the process, although the project is technically fully prepared.
Challenges for Kyrgyzstan and Uzbekistan
Kyrgyzstan and Uzbekistan face financial constraints that hinder independent financing of the project. Kyrgyzstan allocated approximately 483 million soms (about $5.4 million) for the feasibility study completed in summer, which estimated the cost of the Kyrgyz segment at $4.7 billion. The Kyrgyz section covers about 280 kilometers through mountainous terrain with over 50 tunnels and 90 bridges. Uzbekistan is responsible for a roughly 100-kilometer section, which may make financing easier for Tashkent compared to Bishkek.
Political and Economic Implications
Experts point out that a delay in the project could benefit Kyrgyzstan's neighbor Kazakhstan, as the route was originally designed as an alternative for transporting Chinese goods to Russia, bypassing Astana. The current main route for imports from China to Europe goes through Kazakhstan, Russia, and Belarus. A CKU project would cause economic loss to these countries, while Kyrgyzstan and Uzbekistan would gain, creating political hurdles.
Recent Developments and Prospects
Despite the difficulties, Kyrgyz officials deny a temporary suspension of the project. Transport Minister Tilek Tekebaev emphasized that work will resume once the financing model is finalized. Following the BRI summit in China in October and a visit by Chinese Premier Li Qiang to Bishkek, strategic cooperation agreements were signed, including one related to the CKU project, though no details were made public. The Kyrgyz government is considering options such as public-private partnerships or loans, with debts to China's EXIM Bank of around $2 billion seen as a risk.
Project: China-Kyrgyzstan-Uzbekistan Railway · Central Asia (regional) · Under construction · $4.7 bn
Key facts
- Total length of CKU Railway: approx. 454 kilometers
- Kyrgyz section: approx. 280 kilometers, estimated cost $4.7 billion
- Uzbek section: approx. 100 kilometers
- Financing model: Not yet agreed upon by Beijing, Bishkek, and Tashkent
- Kyrgyz feasibility study: Cost 483 million soms (approx. $5.4 million)
- Kyrgyz state debt to Chinese banks: approx. $2 billion