Kazakhstan: Start of construction of the first NPP in Ulken

Investors, volumes and stages of the region's major projects – for European suppliers

· 11 Sources

Scroll
Energy Kazakhstan11 Sources

Published · last updated · 8 Aug 2025 – 13 Aug 2025

On August 8, 2025, engineering survey work began in the village of Ulken, Kazakhstan, for the construction of the country's first nuclear power plant (NPP). The project is led by the Russian state corporation Rosatom, which acts as the leader of an international consortium. Total investment is estimated at 14 to $15 billion, with an additional one billion $ allocated for social infrastructure.

Start of survey work

On August 8, 2025, the first works for the construction of Kazakhstan's first nuclear power plant began in the village of Ulken, Dzhambyl District, Almaty Region. The ceremony was attended by the Director General of Rosatom, Alexey Likhachev, and the Chairman of the Agency for Atomic Energy of the Republic of Kazakhstan, Almasadam Satkaliyev. The works started with the drilling of the first exploration borehole to obtain soil samples. This phase is aimed at selecting the optimal site for the reactors and preparing project documentation.

Technical specifications and location

The NPP will consist of two units with VVER-1200 reactors (Water-Water Energetic Reactor) of Generation III+, each with an electrical capacity of 1200 MW. The reactors are equipped with passive safety systems and a melt trap. Engineering surveys will last at least 18 months and include drilling at least 50 boreholes with a depth of 30 to 120 meters on three pre-selected sites. The goal is to conduct a detailed study of geological, seismic, and hydrological conditions.

Investments and financing

The Chairman of the Agency for Atomic Energy, Almasadam Satkaliyev, stated that investments in the project will amount to approximately 14 to $15 billion. Additionally, around one billion $ is allocated for social projects and infrastructure. The exact financing, including potential state export credits from Russia, will be determined after the completion of the technical and economic feasibility study (TEO), planned for December 2025.

Timeline and jobs

Construction is expected to take about eleven years, with commissioning planned for 2035 or 2036. The service life of the reactors is stated as 60 years, with the possibility of extension by another 20 years. Up to 10,000 jobs are expected during the construction phase, including about 5,000 by 2030 and 2,000 after commissioning. Rosatom states that local Kazakh companies will participate in 30 percent of the works.

Background and further projects

The decision to build the NPP was made through a referendum in October 2024. Rosatom was selected as the winner of the competition in June 2025. Kazakhstan plans to build a total of three NPPs; the second and third plants are to be built by the Chinese state corporation China National Nuclear Corporation (CNNC). The site of the first plant is located on the northwestern shore of Lake Balkhash, where the population currently ranges from 1,600 to 3,000 inhabitants.

Project: Balkhash and Moyinkum nuclear power plants · Kazakhstan · Planned · $16 bn

Key facts

  • Start of survey works: August 8, 2025
  • Location: Ulken village, Dzhambyl District, Almaty Region
  • Technology: Two VVER-1200 reactors (Gen. III+)
  • Estimated investment: 14–$15 billion
  • Social budget: approx. $1 billion
  • Planned commissioning: 2035–2036
  • Reactor service life: 60 years (extendable by 20 years)
  • Number of boreholes: at least 50 (30–120 m depth)
  • Duration of surveys: approx. 18 months
  • Main partner: Rosatom (consortium leader)

All sources (12)

  1. На строительство первой АЭС в Казахстане планируют направить $14-15 млрдИнтерфакс · · RU
  2. "Ростатом" начал строительство первой в Казахстане АЭСDW.com · · RU
  3. Строительство АЭС может обойтись Казахстану в $14-15 млрдReport.az · · RU
  4. Строительство первой АЭС началось в КазахстанеИнтерфакс · · RU
  5. В Казахстане начали строить АЭС: проект обойдется в миллиарды — Деловые новости КазахстанаLSM.KZ · · RU
  6. В Казахстане начались работы по строительству АЭС большой мощностиСтрана Росатом · · RU
  7. В Казахстане начат первый этап проекта по строительству АЭСKapital.kz · · RU
  8. Kazakhstan, Russia launch construction of nuclear power plant in republictass.com · · EN
  9. На берегу Балхаша начались работы по строительству первой атомной электростанцииInbusiness.kz · · RU
  10. Село Улкен перед стартом строительства АЭС: как оно выглядит сегодняКазинформ · · RU
  11. Survey Work Begins in Kazakhstan for Russia-Built Nuclear Power PlantThe Diplomat – Asia-Pacific Current Affairs Magazine · · EN
  12. Kasachstan und Russland starten Arbeiten am ersten kasachischen KernkraftwerkDeutsche Allgemeine Zeitung · · DE

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn