Kazakhstan: Contract Signing for Construction of First NPP Balkhash

Investors, volumes and stages of the region's major projects – for European suppliers

· 18 Sources

Scroll
Energy Kazakhstan18 Sources

Published · last updated · 25 May 2026 – 8 Jun 2026

Russia and Kazakhstan signed an intergovernmental agreement on May 28, 2026, for the construction of the country's first nuclear power plant. The project, estimated at 16.4 to $16.5 billion, will be led by Rosatom near Lake Balkhash.

Contract Signing and Financing

On May 28, 2026, Presidents Vladimir Putin and Kassym-Jomart Tokayev, along with officials Alexei Likhachev and Almassadam Satkaliyev, signed several agreements. These include an intergovernmental agreement on the basic principles of cooperation, a deal on the provision of a Russian state export loan, and an action plan for nuclear and radiation safety cooperation for 2026–2030. The total project cost is estimated at 16.4 to $16.5 billion. Approximately $14.4 billion is allocated for the two energy blocks, and about $2 billion for physical protection systems and social infrastructure. Financing will be largely provided by a Russian state export loan covering up to 85 percent of the costs.

Technical Specifications and Location

The plant, named 'Balkhash', will be built near the village of Ulken on the shores of Lake Balkhash in southeastern Kazakhstan. It will consist of two VVER-1200 III+ reactors with a combined installed capacity of 2.4 GWe. Rosatom will lead the consortium and retain responsibility for core engineering, reactor technology, and key heavy nuclear equipment. However, participation from companies in South Korea, China, and France is being considered for specific areas, while Rosatom maintains core competencies.

Timeline and Construction Process

Active construction is scheduled to begin in 2027, preceded by engineering surveys and documentation preparation for licensing. The first reactor is expected to enter service in early 2034, with the second block following eight to ten months later. Commissioning will occur in stages in the mid-2030s. Kazakhstan aims to have 2.4 gigawatts of nuclear capacity by 2035.

Background and Energy Policy

Kazakhstan, the world's largest uranium producer, has not operated commercial nuclear generation since the shutdown of the BN-350 reactor in Aktau in 1999. Political support was strengthened by a referendum in October 2024, where 71 percent of voters approved nuclear development. The project aims to diversify the coal-heavy power mix, ensure long-term energy security, and support industrial growth with stable baseload power. Concurrently, Kazakhstan has approved a second nuclear plant, awarded to China National Nuclear Corporation (CNNC).

Project: Balkhash and Moyinkum nuclear power plants · Kazakhstan · Planned · $16 bn

Key facts

  • Signing of agreements: May 28, 2026
  • Estimated total cost: 16.4 to $16.5 billion
  • Russian financing share: up to 85 percent via export loan
  • Reactor type: two VVER-1200 III+
  • Installed capacity: 2.4 GWe
  • Location: Ulken village, Lake Balkhash
  • Construction start: 2027
  • First unit commissioning: early 2034

All sources (18)

  1. Kazakhstan's First Nuclear Plant Faces More Delaysoilprice.com · · EN
  2. Строительство первой АЭС в Казахстане обойдется в $16,4 млрдИнтерфакс · · RU
  3. «Проект на $16,5 миллиарда». Россия построит первую АЭС еще в одной странеNV Бизнес · · RU
  4. Russia signs $16.5 billion deal to build first nuclear power plant in KazakhstanReuters · · EN
  5. Kazakhstan’s First Nuclear Power Plant Project Estimated at $16.5 BillionThe Astana Times · · EN
  6. Russia to build first nuclear power plant in Kazakhstan, signs an agreementThe Indian Express · · EN
  7. Россия построит первую АЭС Казахстана за $16,5 миллиардовЕкономічна правда · · RU
  8. Строительство первой АЭС в Казахстане обойдется в $16,4 млрдKapital.kz · · RU
  9. Казахстан заключил договор с РФ о строительстве первой АЭСDW.com · · RU
  10. На строительство первой АЭС в Казахстане потребуется $16,4 млрдBES.media · · RU
  11. Kazakhstan borrows $16.4B from Russia for first nuclear plantKursiv Media · · EN
  12. Russland und Kasachstan unterzeichnen Abkommen über Bau von erstem AtomkraftwerkBerliner Zeitung · · DE
  13. Balkhash Nuclear Power Plant, Kazakhstan's First, Signs $16.5 Billion Construction Deal With RussiaConstruction Review · · EN
  14. Общая стоимость строительства двухблочной АЭС «Балхаш» в Казахстане составит $16,4 млрдАтомная энергия 2.0 · · RU
  15. Kazakhstan partners with Russia for new nuclear power plant -- ANS / Nuclear NewswireAmerican Nuclear Society · · EN
  16. Kazakhstan, Russia Step Forward With $16.4 Billion Nuclear Power Plant PlanThe Diplomat – Asia-Pacific Current Affairs Magazine · · EN
  17. Russia to build Kazakhstan's first nuclear power plant, with Russian loan covering most of the $16.5 billion costoEnergetice.cz · · EN
  18. АЭС в Казахстане обойдётся вдвое дороже, чем в УзбекистанеUlysmedia.kz · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn