Kazakhstan: Construction contract for first Balkhash nuclear power plant signed with Rosatom

Investors, volumes and stages of the region's major projects – for European suppliers

· 7 Sources

Scroll
Energy Kazakhstan7 Sources

Published · last updated · 2 Sep 2026 – 7 Sep 2026

Kazakhstan and the Russian state corporation Rosatom have signed the contract for the construction and equipment of the country's first nuclear power plant. The project, valued at approximately $16.5 billion, includes two VVER-1200 reactors with a total capacity of 2.4 gigawatts. Construction is scheduled to begin in 2027, with the first unit expected to come online in 2034.

Contract Signing and Project Scope

On September 3, 2026, in Vladivostok at the 11th Eastern Economic Forum, the contract was signed between the Kazakh state company Kazakhstan Nuclear Power Plants and the Russian company Atomstroyexport. The contract covers planning, supply, and construction. Rosatom acts as the leader of the international consortium and is responsible for the entire project implementation from design to commissioning. The plant will consist of two VVER-1200 pressurized water reactors with a combined capacity of approximately 2.4 gigawatts.

Location and Timeline

The plant, named Balkhash, will be built in the Zhambyl district of the Almaty Region, near the village of Ulken on the western shore of Lake Balkhash, about 400 kilometers from Almaty. Preparatory works, including drilling for site assessment, began in August 2025. Licensing by Rosatom and the start of construction are scheduled for 2027. The commissioning of the first reactor unit is planned for 2034, with the full construction cycle expected to take about a decade.

Financing and Costs

The total cost of the project is estimated at around 16.4 to $16.5 billion. Approximately $14.4 billion are allocated for the two reactor units, and roughly $2 billion for infrastructure, physical protection systems, and fuel for the warranty period. Financing is primarily provided through a Russian export loan. Kazakhstan is providing its own funds; the draft state budget for 2027–2029 earmarks ₸818.3 billion (approx. $1.7 billion) to increase the capital of Kazakhstan Nuclear Power Plants.

Background and Industrial Development

The construction was approved by the majority of voters in a national referendum in October 2024. Rosatom was selected in June 2025 from a shortlist that included bidders from China, France, and South Korea. The project aims to secure energy supply amid rising demand from digitalization and AI. It also aims to promote local value creation by involving Kazakh companies and specialists in construction and supply chains. Kazakhstan, the world's leading uranium producer, plans to build a second plant with the support of China's CNNC.

Project: Balkhash and Moyinkum nuclear power plants · Kazakhstan · Planned · $16 bn

Key facts

  • Contract signing: September 3, 2026, in Vladivostok
  • Partners: Kazakhstan Nuclear Power Plants and Atomstroyexport (Rosatom)
  • Volume: approx. 16.4–$16.5 billion
  • Capacity: 2.4 gigawatts (two VVER-1200 reactors)
  • Location: Zhambyl district, Almaty Region (near Lake Balkhash)
  • Construction start: 2027
  • First unit commissioning: 2034
  • Financing: Russian export loan and Kazakh state funds ($1.7 billion by 2029)

All sources (7)

  1. Казахстан и Росатом подписали контракт на строительство АЭСKapital.kz · · RU
  2. Проект на $16,5 млрд. Россия планирует начать строительство первой АЭС в дружественной стране в 2027 годуNV Бизнес · · RU
  3. Kazakhstan Nuclear Power Plant Contract Signed with RosatomThe Times Of Central Asia · · EN
  4. Kazakhstan, Rosatom Seal Contract for Two-Unit Balkhash Nuclear Plantcaspiannews.com · · EN
  5. Kazakhstan Signs Contract For Construction Of First Nuclear Power PlantThe Astana Times · · EN
  6. Rosatom signs EPC contract for Kazakhstan nuclear plantWorld Nuclear News · · EN
  7. Kazakhstan has signed a contract for the construction of the country’s first nuclear power stationlogos-pres.md · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn