Uzbekistan: Government reveals plans and costs for first toll highways

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
Transport & logistics Uzbekistan1 Source

Published · last updated · 19 Apr 2026

Uzbekistan has presented detailed plans for its first toll highway network. Key projects include routes from Tashkent to Samarkand, Andijan, as well as to the tourist regions of Charvak and Khiva. Total costs for the individual sections amount to several billion $.

Tashkent–Samarkand connection

The Tashkent–Samarkand toll highway has a value of $2.25 billion and a length of 282 kilometers. The route starts at the Tashkent Ring Road in the Sergeli district and runs parallel to the existing highway. The six-lane road is designed for a target speed of 150 km/h and is expected to handle up to 50,000 vehicles per day. Construction will take five years, reducing travel time to 2–2.5 hours. There will be 12 entry and exit terminals along the route.

Tashkent–Andijan connection

For the 314-kilometer Tashkent–Andijan route crossing the Kamchik Pass, the first phase of 171 kilometers for the Tashkent–Angren–Kamchik section is estimated at $3.66 billion. This includes a new 33-kilometer four-lane tunnel. The World Bank supports the project, and international consulting firm Arup oversees design and tendering. Travel time will drop from 5–5.5 hours to approximately 2–2.5 hours.

Regional links and tariffs

Preliminary agreements for the 52-kilometer Tashkent–Charvak toll road have been reached with Qatar’s Protocol Group and the Korea Expressway Corporation. Construction takes three years, reducing travel time from 80 to 35 minutes. In western Uzbekistan, construction began in February on the 35-kilometer Urgench–Khiva toll road for $120 million. It is four-lane and will reduce travel time from one hour to 17 minutes. Tariffs are not yet finalized; a pricing methodology with a ceiling is being developed by the Committee for Roads.

Project: Uzbekistan Toll Highway Network · Uzbekistan · Planned · $6.2 bn

Key facts

  • Tashkent–Samarkand toll road: $2.25 billion, 282 km, 5 years construction
  • Tashkent–Andijan toll road (Phase 1): $3.66 billion, 171 km, 33 km tunnel
  • Tashkent–Charvak toll road: 52 km, 3 years construction, partners: Protocol Group, Korea Expressway Corp.
  • Urgench–Khiva toll road: $120 million, 35 km, construction started February 2026

All sources (1)

  1. Government reveals preliminary costs and plans for Uzbekistan’s first toll highwaysKun.uz · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn