Uzbekistan: Construction of Tashkent–Charvak Toll Road Planned

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
Transport & logistics Uzbekistan1 Source

Published · last updated · 16 Mar 2026

Uzbekistan plans to build a 52-kilometer toll road from New Tashkent to the Charvak reservoir. Construction is expected to take three years, with commissioning targeted for 2029. Preliminary agreements have been reached with Qatari and South Korean partners.

Project Scope and Timeline

The project involves the construction of a 52-kilometer, six-lane Category 1A highway with cement concrete pavement from New Tashkent to the Charvak reservoir. The planned construction period is three years, with commissioning expected in 2029. Initial lengths of 56 km and later 82 km were discussed, but the current route is 52 km. The maximum speed limit is 150 km/h. The road is projected to handle approximately 250,000 vehicles annually, reducing travel time from about 80 minutes to 35 minutes.

Involved Companies and Status

Preliminary agreements have been reached with Qatar's Protocol Capital Group and South Korea's Korea Expressway Corporation. Protocol Capital Group holds assets exceeding $4 billion and has implemented over 1,000 projects globally. Korea Expressway Corporation manages toll roads in South Korea. The project company Autoyulinvest, under the Ministry of Transport, is currently preparing project documentation and has engaged international consulting firms for the design phase.

Background and Further Plans

The new route aims to relieve tourist traffic to the reservoir and avoid existing congestion on this corridor. A potential second phase of 9 km is planned to extend towards the proposed Sea Breeze complex. Concurrently, other infrastructure projects such as the Tashkent–Samarkand toll road or the Tashkent–Angren–Kamchik route ($3.66 billion) are under discussion, with tariffs and start dates still being negotiated.

Project: Tashkent–Charvak Toll Road · Uzbekistan · Planned

Key facts

  • Route length: 52 km
  • Construction time: 3 years
  • Commissioning: 2029
  • Max. speed: 150 km/h
  • Traffic volume: approx. 250,000 vehicles/year

All sources (1)

  1. До Чарвака за 35 минут: платную дорогу из Ташкента планируют построить за три годаГазета.uz · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn