Uzbekistan has commenced the active construction phase of the integrated nuclear power plant in the Jizzakh region. The project, valued at $9.5 billion, includes two large VVER-1000 and two small RITM-200N reactors. President Shavkat Mirziyoyev has mandated an increase in local content to at least 30 percent.
Project Scope and Configuration
The integrated nuclear power plant in the Jizzakh region reached the active construction phase on June 4, 2026. The total investment volume is $9.5 billion. The facility combines two large VVER-1000 reactors with 1,000 MW each for baseload and two small RITM-200N reactors with 55 MW each for peak load. The planned annual electricity generation is approximately 15.4 to 17 billion kWh, representing more than 15 percent of national consumption. Commissioning is scheduled for 2035.
Construction Progress and Infrastructure
On a site area of 525 hectares, excavation for the reactor building has been completed, with over one million cubic meters of soil removed. 916 cubic meters of concrete were poured for the foundation slab. Concurrently, 388 km of electrical networks, 120 km of water pipelines, 39.5 km of roads, and 11 km of railways are being constructed. A new town district with 10,000 apartments for approximately 33,000 residents is planned on 200 hectares for construction workers.
Localization and Industrial Zone
President Shavkat Mirziyoyev deemed the current local participation of 21 percent ($1.9 billion) insufficient and ordered an increase to at least 30 percent. National enterprises are to carry out 65 percent of construction and installation work and 60 to 70 percent of infrastructure services. A 200-hectare industrial zone in the Forish district has been approved, which is expected to receive tax and customs incentives by the end of 2026.
Actors and Financing
The client is the Directorate for Nuclear Power Plant Construction under the "Uzatom" agency, with Rosatom's engineering division as the executing company. Financing remains open, as Russian proposals were evaluated as unattractive by Tashkent. The establishment of a joint venture with international engineering firms for technical control and independent review is being discussed to reduce dependence on Rosatom.
Personnel and Regulatory Framework
Up to 7,000 local workers are to be employed, with the share of domestic specialists targeted at 65 to 70 percent. Since 2023, 216 students have graduated from the Tashkent branch of the National Research Nuclear University MEPhI. The project follows IAEA milestones, and the environmental impact assessment has been completed. The license for the construction of the small reactors was issued in March 2026.
Project: High-capacity nuclear power plant Uzbekistan · Uzbekistan · Under construction · $9.5 bn
Key facts
- Total volume: $9.5 billion
- Active construction start: June 4, 2026
- Reactor types: 2x VVER-1000 (1,000 MW), 2x RITM-200N (55 MW)
- Local content target: at least 30 percent
- Forish industrial zone: 200 hectares, approved by end of 2026
- Construction jobs: up to 7,000 local specialists
- Worker town: 10,000 apartments for 33,000 residents
- Infrastructure: 388 km power lines, 120 km water pipelines
All sources (13)
- Международное агентство по атомной энергии (МАГАТЭ) по итогам повторной миссии отметило значительный прогресс Узбекистана в развитии инфраструктуры для атомной …Gazeta.uz (Telegram) · · RU
- Бюджет «Узатома» и дирекции АЭС на 2026−2027 годы пересмотрятГазета.uz · · RU
- Рассмотрены ход строительства АЭС и проект города атомщиковpresident.uz · · RU
- Jizzakh Nuclear Power Plant Project Costs US$9.5bnUzDaily.uz · · EN
- Строительство АЭС в Узбекистане за $9,5 млрдKursiv Media Узбекистан · · RU
- Uzbekistan Nuclear Power Plant Targets More Local Production in $9.5 Billion ProjectThe Times Of Central Asia · · EN
- Общая стоимость проекта АЭС в Джизаке — $9,5 млрдKun.uz · · RU
- Industrial zone plan to boost localisation for Uzbek nuclear projectWorld Nuclear News · · EN
- Проект АЭС в Узбекистане оценили в $9,5 млрд. Мирзиёев поручил нарастить долю узбекской продукции в стоимости до 30% — Тазабек CATazabek.KG · · RU
- Uzbekistan begins active construction phase on $9.5 billion integrated nuclear power plant projectAKIpress News Agency · · EN
- Uzbekistan Scales Back Nuclear Cooperation With RussiaCrude Oil Prices Today | OilPrice.com · · EN
- Uzbekistan Plans Joint Venture to Oversee Nuclear Power PlantThe Times Of Central Asia · · EN
- China is Uzbekistan's choice for second nuclear plant project, reveals Serbia's presidentmsn.com · · EN