Uzbekistan: Construction start of integrated NPP in Jizzakh region

Investors, volumes and stages of the region's major projects – for European suppliers

· 24 Sources

Scroll
Energy Uzbekistan24 Sources

Published · last updated · 2 Jun 2026 – 10 Jun 2026

Uzbekistan and Russia officially commenced construction of the first integrated nuclear power plant in the Jizzakh region on June 4, 2026. The ceremony marking the pouring of the foundation concrete for the first power unit served as the symbolic start. The project comprises two large VVER-1000 reactors and two small RITM-200N modules.

Construction Start and Technical Configuration

On June 4, 2026, the symbolic pouring of the first foundation concrete for the first power unit of the integrated nuclear power plant took place in the Ferish district of the Jizzakh region. The project is unique globally as it combines large and small nuclear power units on a single site. The facility will consist of two large power units with VVER-1000 reactors, each with 1,000 MW capacity, and one unit with two RITM-200N reactors, each with 55 MW. The ceremony was conducted as a telebridge between the construction site in Uzbekistan and St. Petersburg.

Financing and Costs

The base construction cost of the integrated NPP is estimated at no more than $9.5 billion. Russia will provide Uzbekistan with a preferential export loan. According to Azim Akhmedkhadjaev, 85 to 90 percent of the project cost will be financed through credit funds, with a portion coming from the state budget. Calculations were conducted in collaboration with partners from the so-called 'Big Four'.

Production Capacity and Jobs

Once operational, the plant will generate approximately 17 billion kilowatt-hours of electricity annually, covering up to 15 percent of Uzbekistan's energy consumption. Around 15,000 jobs are planned for the construction site. Local contractors will be actively involved in installation, material supplies, and transport services. Technology transfer to sectors such as agriculture and medicine is also anticipated.

Regulatory Approvals

The construction aligns with International Atomic Energy Agency (IAEA) standards. The Committee for Industrial, Radiation and Nuclear Safety under the Cabinet of Ministers of Uzbekistan has already issued a license to the Directorate for NPP Construction for the power unit with the Russian RITM-200N nuclear installation. Project documentation and safety justifications were reviewed at the Scientific and Technical Center for Radiation and Nuclear Safety. On March 23, 2026, permission for the use of sites for nuclear installations was also granted.

Personnel Training and Lifecycle

Russia assumes obligations for the long-term supply of reactor fuel, maintenance, and management of spent nuclear fuel. To qualify personnel, approximately 400 Uzbek citizens are being trained in Russian universities in nuclear engineering, with over 300 additional students studying at the Tashkent branch of the National Research Nuclear University MIFi. The plant is intended to form the basis of a national high-tech nuclear industry in Uzbekistan.

Project: High-capacity nuclear power plant Uzbekistan · Uzbekistan · Under construction · $9.5 bn

Key facts

  • Construction start: June 4, 2026
  • Location: Ferish district, Jizzakh region
  • Reactor types: Two VVER-1000 (each 1,000 MW), two RITM-200N (each 55 MW)
  • Estimated construction cost: Up to $9.5 billion
  • Financing: Preferable export loan from Russia (85-90% of costs)
  • Annual production: Approx. 17 billion kWh
  • Energy coverage: Up to 15%
  • Jobs (construction): Approx. 15,000
  • Approval: License from the Committee for Industrial, Radiation and Nuclear Safety

All sources (33)

  1. Presidents of Russia, Uzbekistan to give start to NPP construction — Kremlin aidetass.com · · EN
  2. Presidents of Uzbekistan and Russia to launch NPP construction in Jizzakh region at St Petersburg ceremonyГазета.uz · · EN
  3. В Узбекистане выдана лицензии на строительство энергоблока малой атомной станции с реактором РИТМ-200НGazeta.uz (Telegram) · · RU
  4. Стоимость строительства интегрированной АЭС в Узбекистане не превысит $9,5 млрд — «Узатом»Газета.uz · · RU
  5. Стоимость интегрированной АЭС в Узбекистане составит $9,5 млрд — глава «УзатомаSpot.uz · · RU
  6. Узбекистан выдал лицензию на строительство энергоблока АЭС с реактором RITM-200NИнтерфакс · · RU
  7. Начало строительства первого энергоблока интегрированной АЭС в УзбекистанеПрезидент России · · RU
  8. "Росатом" начал строительство АЭС в УзбекистанеИнтерфакс · · RU
  9. Russia, Uzbekistan start construction of nuclear power plantReuters · · EN
  10. Launch of construction of the first power unit of the integrated NPP in UzbekistanПрезидент России · · EN
  11. Стоимость АЭС в Узбекистане составит $9,5 млрдUzDaily · · RU
  12. Стоимость строительства АЭС в Узбекистане не превысит $9,5 млрдРитм Евразии · · RU
  13. Узбекистан ищет $9,5 млрд для строительства АЭСUlysmedia.kz · · RU
  14. Стоимость интегрированной АЭС в Узбекистане оценили в $9,5 млрдBAQ.KZ · · RU
  15. «Общая стоимость строительства АЭС составит $9,5 млрд» — Азим АхмедходжаевDaryo · · RU
  16. Строительство первой АЭС началось в УзбекистанеКазинформ · · RU
  17. В «Узатоме» назвали стоимость строительства интегрированной АЭСKun.uz · · RU
  18. Россия предоставит Узбекистану льготный экспортный кредит на строительство АЭС — ПутинГазета.uz · · RU
  19. Путин и Мирзиёев дали старт строительству первой АЭС в УзбекистанеKursiv Media · · RU
  20. Глава «Узатома» раскрыл стоимость первой АЭС в УзбекистанеPodrobno.uz · · RU
  21. Президенты Узбекистана и России дали старт строительству первого энергоблока АЭСГазета.uz · · RU
  22. «Безопасность при строительстве АЭС является абсолютным и безусловным приоритетом» — президентГазета.uz · · RU
  23. Russia And Uzbekistan Begin Construction Of First ‘Integrated’ Nuclear Power PlantNucNet · · EN
  24. Uzbekistan starts construction of its first nuclear power plantQazinform · · EN
  25. Uzbek and Russian leaders launch construction of first nuclear power unit in UzbekistanАзия-Плюс · · EN
  26. Uzbekistan caps integrated nuclear power plant cost at $9.5 billionKun.uz · · EN
  27. Presidents of Uzbekistan, Russia launch construction of nuclear power plant in UzbekistanГазета.uz · · EN
  28. Ceremony to mark first concrete for Uzbekistan SMRWorld Nuclear News · · EN
  29. Uzbekistan Nuclear Plant Cost Set at US$9.5 BillionUzDaily · · EN
  30. Moskau finanziert Usbekistans erstes AtomkraftwerkDiePresse.com · · DE
  31. Uzbekistan, Russia Celebrate Start of Nuclear Power Plant Construction… AgainThe Diplomat – Asia-Pacific Current Affairs Magazine · · EN
  32. Putin, Mirziyoyev Launch Construction of Uzbekistan's First Nuclear Power Plantcaspiannews.com · · EN
  33. Rosatom starts construction of the world’s first export small modular nuclear power plant in UzbekistanNamibia Economist · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn