Approximately $1 billion is being attracted for the continuation of the construction of 'Rogun' to build remaining structures on the right bank. President Emomali Rahmon expressed confidence in the commissioning of the third unit of the Rogun HPP in 2027. The World Bank document regarding this funding does not indicate that a new loan or grant has been allocated.
Sustainable financing for the construction of remaining right bank structures (Lot 3A) is estimated at approximately $1 billion. Procurement procedures for 'Lot 3A' have passed several planned stages, including preliminary selection in late 2025 and contractor selection in 2026. The contract signature date is listed as August 13, 2026, and the document was published on September 6, 2026. The estimated contract completion deadline is February 4, 2028.
Works include the construction of hydraulic structures, spillways, related tunnels, and hydromechanical equipment. The Rogun HPP is being built on the Vakhsh River. After the completion of the project, the installed capacity of the power plant should be 3780 MW. More than 20 thousand workers and engineering and technical specialists are involved in the construction.
Emomali Rahmon announced that 60.3 billion somoni have already been allocated to the facility since the start of construction. In August, rating agency 'S&P Global Ratings' estimated the remaining funding needs to complete the project at approximately $5.8 billion. President Emomali Rahmon stated that with continued construction, the third unit will be commissioned in 2027.
Project: Rogun HPP · Tajikistan · Under construction · $6.4 bn
Key facts
- Funding for Lot 3A is estimated at $1 billion.
- Contract completion deadline is February 4, 2028.
- Total installed capacity after completion will be 3780 MW.
- 60.3 billion somoni have been allocated since construction start.
- Over 20,000 workers are involved in construction.
- S&P Global Ratings estimates remaining funding needs at $5.8 billion.
All sources (3)
- Президент Республики Таджикистан выразил уверенность в вводе в эксплуатацию третьего агрегата Рогунской ГЭС в 2027 годуАМИТ "Ховар" · · RU
- ⏺Барои идомаи сохтмони “Роғун” 1 млрд доллари дигар ҷалб мекунандAsia-Plus (Telegram) · · UZ
- Барои идомаи сохтмони "Роғун" 1 млрд доллари дигар ҷалб мекунанд - Азия-Плюсasiaplus.news · · UZ