Tajikistan: Progress and Financing of the Rogun HPP Project

Investors, volumes and stages of the region's major projects – for European suppliers

· 6 Sources

Scroll
Energy Tajikistan6 Sources

Published · last updated · 17 Aug 2026 – 25 Aug 2026

Tajikistan expects the commissioning of Rogun HPP unit No. 3 in September 2027. S&P Global Ratings estimates that an additional $5.8 billion is required to complete the Rogun HPP by 2035. President Emomali Rahmon has ordered the dam height to be raised by 30 meters by 2027 and instructed contractors to accelerate work on various lots to ensure timely completion.

Construction Progress and Technical Milestones

As of August 21, 2026, material has been laid in the dam body up to the 1,155-meter mark, reaching a height of 190 meters. Since the beginning of construction, more than 49 million cubic meters of material have been laid, representing over 61% of the project volume. Transport tunnel T-39, which connects the right bank, the lower part of the dam, and the left bank, has been fully commissioned. Excavation, temporary support, reinforcement, and concreting in the construction tunnel of the fourth tier have been completed, and the tunnel is ready for water passage. More than 5,944 modern control and measuring instruments have been installed and mounted at the site.

Financing and Investment

The cost of completing the Rogun HPP by 2035 is estimated at approximately $5.8 billion. The government of Tajikistan has agreed with a consortium of multilateral and bilateral partners on financing that will cover about 50% of this amount. The remaining half of the costs is expected to be covered from the state budget and revenues generated by the Rogun HPP itself.

Project: Rogun HPP · Tajikistan · Under construction · $6.4 bn

Key facts

  • The Rogun HPP is located on the Vakhsh River.
  • The 335-meter high dam will be the highest rock-fill dam in the world.
  • Active construction phase has been underway since the 2000s.
  • Today, more than 20,000 workers and engineering-technical staff work at the site, and the number of machines and mechanisms has reached 4,000 units.
  • International experts are considering the need to build an additional protective dam.
  • Expenses are influenced by inflation, cost of materials and equipment, complex geology, and additional safety requirements.

All sources (10)

  1. В Таджикистане ввод энергоблока №3 Рогунской ГЭС ожидается через годИнтерфакс · · RU
  2. На достройку Рогуна потребуется еще $5,8 млрд — S&PАзия-Плюс · · RU
  3. Эмомали Рахмон: «Рогун» должны завершить в установленные сроки - Новости ТаджикистанаAvesta.tj · · RU
  4. AP30/Истории. Второе рождение Рогуна. Как 20 лет назад президент Таджикистана дал старт стройке векаАзия-Плюс · · RU
  5. На Рогунской ГЭС ввели в эксплуатацию тоннель Т-39 — Тазабек CATazabek.KG · · RU
  6. Эмомали Рахмон поручил за год поднять плотину Рогунской ГЭС еще на 30 метровАзия-Плюс · · RU
  7. Выступление Президента Республики Таджикистан, Лидера нации уважаемого Эмомали Рахмона на встрече со строителями Рогунской гидроэлектростанцииАМИТ "Ховар" · · RU
  8. Президент Таджикистана проверил ход работ на ключевых объектах Рогунской ГЭСAvesta.tj · · RU
  9. В сентябре 2027 года планируется сдать в эксплуатацию четвёртый агрегат Рогунской ГЭСАМИТ "Ховар" · · RU
  10. Rogun Dam reaches 1,155 metres above sea level | Webuild GroupWebuild Group · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn