Construction has begun on two new cement plants in the Varesch region, developed by «Dushanbe Cement» and «Tajik Cement». The projects are scheduled for completion within 17 months, providing a combined annual capacity of 2.4 million tons.
Construction Start
On June 23, 2026, Tajik President Emomali Rahmon and the Chairman of the National Assembly and Mayor of Dushanbe, Rustam Emomali, inaugurated the construction of two new cement plants in the village of Charangoni-Bolo in the Varesch district. The projects are implemented under a state directive issued at a government session on May 28, 2026, aiming to establish four new facilities with a combined annual capacity of six million tons.
Project Structure and Investors
The first plant is being built by Limited Liability Company «Dushanbe Cement» on an 18-hectare site in the south of Charangoni-Bolo. The second project, developed by «Tajik Cement» (Russian: «Sementi Tochik»), is located on a 16-hectare plot in the north of the same village. Both sites are situated near deposits of limestone, magnetite, and clay.
Technical Specifications and Timeline
Both facilities are scheduled for completion and commissioning within 17 months. Each plant will have an annual production capacity of 1.2 million tons of cement, equivalent to 3,300 tons per day. The production cycle covers the entire process from raw material processing to finished product packaging. Construction, technology supply, and equipment procurement are funded entirely by domestic investments.
Technological Partnership
Planning, equipment supply, installation, and commissioning will be carried out in cooperation with the Chinese company SINOMA. SINOMA is described as a major state corporation and international engineering service provider, ranking among the world's leading suppliers of cement technology and equipment. The facilities are designed to meet European and international quality and environmental safety standards.
Employment and Economic Context
The construction phase will create over 2,600 jobs in total, with more than 1,150 for the first plant and over 1,100 for the second. After commissioning, each site will provide more than 1,000 permanent jobs. The capacity expansion addresses a persistent shortage of cement on the domestic market and rising prices, despite national production capacity already exceeding five million tons per year.
Project: Construction of four new cement plants in Tajikistan · Tajikistan · Under construction
Key facts
- Construction start: June 23, 2026
- Location: Charangoni-Bolo village, Varesch district, Tajikistan
- Investors: LLC «Dushanbe Cement» and LLC «Tajik Cement»
- Capacity per plant: 1.2 million tons per year (3,300 tons/day)
- Construction period: 17 months
- Technology supplier: SINOMA (China)
- Area: 18 hectares (Plant 1) and 16 hectares (Plant 2)
- Jobs (Construction): >2,600 total
All sources (3)
- В Варзобе началось строительство новых цементных заводов (ДОПОЛНЕНО)Азия-Плюс · · RU
- Эмомали Рахмон дал старт строительству двух цементных заводов в Варзобе - Новости ТаджикистанаAvesta.tj · · RU
- Лидер нации Эмомали Рахмон и Председатель города Душанбе Рустами Эмомали в Варзобском районе дали старт строительству предприятия по выпуску цементаАМИТ "Ховар" · · RU