Tajikistan: Construction Start and Launch of New Cement and Lime Plants

Investors, volumes and stages of the region's major projects – for European suppliers

· 2 Sources

Scroll
Mining & metals Tajikistan2 Sources

Published · last updated · 9 Jul 2026

Construction of the ore processing plant for Tajik Steel in the Sogd region is progressing. Concurrently, President Emomali Rahmon launched the construction of a cement plant in Ishtikhon and a lime plant in the Bobojon Ghafurov district.

Progress at Ore Processing Plant

President Emomali Rahmon visited the construction site of the ore processing plant for Tajik Steel in the Bobojon Ghafurov district on July 9, 2026. Work on the first phase, started in April 2025, is over 80 percent complete. The first phase is scheduled for completion in September 2027, and the second phase in 2029. The President ordered the immediate start of the second phase to bring commissioning forward by one year.

Capacities and Investment Volume

The total investment volume for the metallurgical complex is approximately 6 billion somoni. The planned annual capacity is 2.5 million tons of iron ore mining and processing. The first step involves producing iron ore concentrate and pellets, followed by iron ore briquettes, blooms, and rebar. Over 1,200 jobs will be created during construction, rising to more than 1,500 permanently.

New Cement and Lime Production

Parallel to the metallurgical project, Rahmon launched the construction of a cement plant in Ishtikhon and a lime plant in Bobojon Ghafurov. The cement plant will have an annual capacity of 1.2 million tons and is to be completed by 2029. The lime plant, near the Safedsang limestone deposit, will produce 200,000 tons per year. Both projects are scheduled for completion by 2029.

Participating Companies and Technology

The Chinese company NETC acts as the general contractor for the metallurgical complex, supported by Electrotherm (India) for briquetting technology and SPS (Austria) for quality control. SINOMA (China) is responsible for the cement and lime plants. Equipment is sourced from Germany, France, the USA, Japan, Switzerland, and Sweden, among others.

Infrastructure and Resources

A 14.3 km high-voltage line (220 kV) and a 17.5 km water pipeline have been built for the metallurgical complex. The Shokadam deposits contain 59 million tons of confirmed reserves. A 90 MW energy center will cover energy needs. The cement plant will employ 1,200 seasonal workers, and the lime plant 500.

Project: Ore processing plant of the Tajik Metallurgical Combine · Tajikistan · Under construction

Key facts

  • Total investment Metallurgical Complex: approx. 6 billion somoni
  • Annual ore processing capacity: 2.5 million tons
  • Metallurgical Complex completion: 2028 (early)
  • Cement plant capacity: 1.2 million tons/year
  • Lime plant capacity: 200,000 tons/year
  • Confirmed ore reserves: 59 million tons
  • Energy center: 90 MW capacity
  • High-voltage line: 14.3 km at 220 kV

All sources (4)

  1. Лидер нации Эмомали Рахмон в Бободжон Гафуровском районе ознакомился с ходом строительства металлургического предприятия ЗАО «Таджикский металлургический комбинатАМИТ "Ховар" · · RU
  2. В Согде построят заводы по производству цемента и известиAvesta.tj · · RU
  3. Выступление Президента Республики Таджикистан, Лидера нации, уважаемого Эмомали Рахмона на встрече в ходе ознакомления со строительством предприятия по обогащению железной руды в Бободжон Гафуровском районеАМИТ "Ховар" · · RU
  4. Глава государства Эмомали Рахмон в дистанционном формате дал старт строительству предприятий по производству цемента в городе Истаравшане и по производству извести в Бободжон Гафуровском районеАМИТ "Ховар" · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn