The gas power plant within the 247-MW hybrid power complex in Zhanaozen has begun supplying electricity to the grid. Three gas engine-generator units have been successfully synchronized and tested. The construction phase is 98.3% complete.
The gas power plant in the Mangystau region has commenced electricity generation and fed power into the grid. Load tests for the three gas engine-generator units, each with a rated capacity of 20 MW, were successful. Over 500,000 kWh of electricity were generated, confirming synchronization with the grid. The overall construction phase of the gas power plant is 98.3% complete.
Supporting infrastructure, including the 110-kV substation, gas pipelines, and communication lines, has also been completed. Tests for three additional gas units and comprehensive commissioning of the facility remain pending. Since the start of construction, 2.7 million man-hours have been recorded without lost-time injuries, with over 1,000 people employed during the peak construction period.
The project is implemented jointly with the Italian company Eni and comprises 50 MW of solar, 120 MW of gas, and 77 MW of wind power. While the solar plant has generated approximately 75 million kWh since September 2025, foundation work and equipment deliveries are underway for the wind component. Upon completion, the project is expected to create 77 permanent jobs.
Project: Zhanaozen hybrid power complex · Kazakhstan · Under construction
Key facts
- Capacity: 247 MW hybrid complex (120 MW gas, 77 MW wind, 50 MW solar)
- Gas plant progress: 98.3% complete
- Jobs: 77 permanent positions upon completion
- Location: Zhanaozen, Mangystau region, Kazakhstan