Kazakhstan has appointed QazaqGaz as the sole project operator for the construction of a new gas processing plant at the Karachaganak field. The project aims to secure domestic commercial gas supply and reduce dependence on Russian infrastructure. The planned annual capacity is up to 4 billion cubic meters, with an option to increase to 5 billion cubic meters.
New operator structure and partnership
The national company QazaqGaz has taken on the role of the sole project operator for the construction of the gas processing plant (GPP). China’s CITIC Construction has expressed readiness to participate in the project, and a framework agreement outlining the basic principles of cooperation has been signed. The project's economic feasibility has been confirmed, and preparations for the FEED (Front-End Engineering Design) stage are underway. Open issues include land allocation, infrastructure, and feedstock supply.
Capacity and strategic background
The original plan called for commissioning by 2028, with Shell and Eni designated as construction companies. In March 2026, Kazakhstan withdrew from this arrangement due to significant cost overruns and disagreements over implementation terms. Currently, gas is processed at the Russian GPP in Orenburg. The goal of relocating processing to Kazakh territory is to strengthen energy security and reduce dependence on external infrastructure, particularly amid periodic disruptions from drone attacks. The capacity of the future plant could be increased to 5 billion cubic meters per year.
Negotiations and legal disputes
Particular attention is being paid to negotiations with foreign shareholders in the Karachaganak project. Key issues include guaranteed raw gas supplies, establishing a pricing mechanism for the domestic market, integration into existing infrastructure, and clarifying the gas evacuation fee mechanism. The project is part of Kazakhstan's Comprehensive Gas Industry Development Plan through 2029 and is being implemented on the instructions of President Kassym-Jomart Tokayev. Energy Minister Yerlan Akkenzhenov emphasized the need for swift implementation in the interest of national economic interests. Concurrently, international arbitration proceedings are ongoing, in which Shell and Eni may be required to pay between 2 and $4 billion to the Kazakh government.
Project: Karachaganak Gas Processing Plant · Kazakhstan · Under construction · $6.0 bn
Key facts
- Operator: QazaqGaz (sole project operator)
- Partner: China’s CITIC Construction (framework agreement signed)
- Planned capacity: Up to 4 billion m³/year, option for 5 billion m³/year
- Target commissioning: Originally 2028 (current status: FEED preparation)
- Background: Exit of Shell and Eni in March 2026 due to cost overruns
- Legal risks: Arbitration proceedings with Shell and Eni over 2–$4 billion
All sources (1)
- Kazakhstan Appoints Operator for Karachaganak Gas Processing Plant ConstructionThe Times Of Central Asia · · EN