Kazakhstan: FID for Butadiene Plant in Atyrau with Investment Volume Over $1 Billion

Investors, volumes and stages of the region's major projects – for European suppliers

· 4 Sources

Scroll
Chemicals & fertiliser Kazakhstan4 Sources

Published · last updated · 10 Jul 2025 – 16 Jul 2025

Tatneft has issued the Final Investment Decision (FID) for the construction of a butadiene plant in the Atyrau region. The project volume exceeds $1 billion, with a planned annual capacity of 186,000 tons. Commissioning is scheduled for 2027.

Financing and Project Status

Tatneft has issued the Final Investment Decision (FID) for the construction of a chemical plant for the production of butadiene and its derivatives in Atyrau, Kazakhstan. The investment volume is stated at more than $1 billion. The planned production capacity is 186,000 tons per year. The next step is the selection of an EPC contractor by the end of 2025.

Production Program and Market

In addition to the base substance butadiene, 60,000 tons of divinylstyrene synthetic rubber (SBS), 40,000 tons of styrene-butadiene-styrene rubber (SBS), and 40,000 tons of methyl tert-butyl ether (MTBE) are to be produced annually. The products are intended for the rubber industry, tire manufacturing, road construction, and plastic production. Sales will take place on the local Kazakh market as well as for export to Russia, the EU, China, and Turkey.

Participating Companies and Technology

The project is realized through the company TOO „Butadien“, in which Tatneft holds 75% and Samruk-Kazyna Ondeu holds 25%. Tatneft manages operations. The process license is provided by the US firm Lummus Technology. For preliminary planning (pre-FEED), the project works with the Chinese engineering service provider China Tianchen Engineering Corporation.

Raw Material Supply and Infrastructure

Raw material supply is to be provided via the Tengiz and Korolev fields, operated by Tengizchevroil. The plant is part of the strategic cooperation between Kazakhstan and Russia to deepen industrial collaboration. Meanwhile, Tatneft already operates a tire plant in Sarani (Karaganda region), which can be a potential buyer of local rubber production.

Background and Political Context

Cooperation between Tatneft and Kazakhstan began in 2021 with the formation of a joint venture. After disputes over the ownership structure and processing level, Tatneft took full control. The project is supported by the Kazakh government. However, experts express concerns regarding the adherence to the 2027 schedule and cost development due to international sanctions and supply chain issues.

Project: Environmental modernization Atyrau Refinery · Kazakhstan · Under construction · $1.0 bn

Key facts

  • Financing: > $1 billion
  • Capacity: 186,000 t/a butadiene
  • Commissioning: 2027 (planned)
  • Owners: Tatneft (75%), Samruk-Kazyna Ondeu (25%)
  • Technology: Lummus Technology (USA)
  • EPC Pre-planning: China Tianchen Engineering Corporation

All sources (4)

  1. Завод бутадиена в РК построят в АтырауInbusiness.kz · · RU
  2. «Татнефть» приняла решение по строительству бутадиенового завода в АтырауForbes.kz · · RU
  3. Решение принято: в Атырауской области построят завод по выпуску бутадиенаOrda.kz · · RU
  4. Прорыв в Казахстан: зачем «Татнефти» бутадиеновый завод в Атырау за $1 миллиардБИЗНЕС Online — Новости Казани · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn