The company behind the 'Taraz Sulphuric Acid Plant' has postponed the start of construction to the first quarter of 2027, shifting the deadline by six months from the previously planned third quarter of 2026. Construction of a plant with an output of 800 thousand tons of sulfuric acid per year will be launched in the first quarter of 2027.
Construction of the enterprise will begin in the first quarter of 2027, with work expected to last 25 months. The plant is scheduled to begin operations in the second quarter of 2029, with post-utilization and equipment replacement set for 2053. The facility will produce a maximum of 2,400 tons of sulfuric acid per day, operating for approximately 8,000 hours or 334 days a year. The sulfuric acid produced will have a concentration of 99.5-99.9%.
The plant will be built on a 15.5431-hectare land plot in the industrial zone of Taraz, the regional center of the Zhambyl region. LLC 'Taraz Sulphuric Acid Plant' is owned by entrepreneurs Vladimir Kim and Eduard Ogay, as well as Russians Mikhail Genkin, Sergey Momtselidze, and Evgeny Shavel.
The company previously submitted a loan application to JSC Development Bank of Kazakhstan, which was approved at the stage of banking expertise 'indicative analysis'. The largest supplier of sulfur in Kazakhstan is Tengizchevroil LLP, which develops the Tengiz field.
Project: Taraz Sulfuric Acid Plant · Kazakhstan · Planned
Key facts
- Construction start date: First quarter of 2027
- Annual production capacity: 800,000 tons of sulfuric acid
- Daily production capacity: 2,400 tons
- Location: Industrial zone of Taraz, Zhambyl region
- Land plot size: 15.5431 hectares
- Expected operational start: Second quarter of 2029