Digital & telecom

Kazakhstan: Data Center Valley and Energy Challenges

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
Digital & telecom Kazakhstan1 Source

Published · last updated · 4 Sep 2026

U.S.-based Firebird.ai and state-controlled Kazakhtelecom are developing 'Data Center Valley' near Ekibastuz, with an initial 50-megawatt facility scheduled for June 2027. At full capacity, the project could consume 8.8 terawatt-hours annually, estimated by Kazakh media Qyzyq as around 7% of Kazakhstan's current electricity generation.

Project Development and Partners

The project site is currently a construction site located a few kilometers from Ekibastuz, a mining city in northern Kazakhstan. From 2027, the site is scheduled to become the first part of a giant artificial intelligence campus. U.S.-based Firebird.ai and state-controlled Kazakhtelecom are leading the industrial project. No major named customer contract has been announced, although Firebird says it holds guaranteed service contracts with global players. Amazon and G42 have been named as companies entering the ecosystem, while Kazakhstan has also held talks with Microsoft and OpenAI.

Energy Demand and Supply

The project, known as 'Data Center Valley', is expected to eventually reach a capacity of one gigawatt. At full capacity, the project could consume 8.8 terawatt-hours annually, estimated by Kazakh media Qyzyq as around 7% of Kazakhstan's current electricity generation. Development will be gradual, with an initial 50-megawatt facility scheduled to enter service in June 2027. The ministry says data center projects will enter electricity calculations from 2027, the same year the first facility is due to start operating. When the government prepared its 2026 electricity forecast, neither 'Data Center Valley' nor any other AI or data-center project was included.

Coal Infrastructure and Expansion

Nearby lies Bogatyr, one of the world’s largest open-pit coal mines. Yevgeny Masternak, CEO of mine operator Bogatyr Komir, stated that Ekibastuz is a smart choice due to abundant and cheap energy and limited transmission losses. To keep pace with anticipated demand, Bogatyr Komir plans to raise annual coal production from 42 million tonnes in 2024 to more than 56 million by 2032. Bogatyr Komir plans to invest almost $780 million more by 2032 in machinery, conveyors, and mine upgrades. One crucial project is GRES-3, a planned 2.6-gigawatt coal plant in Ekibastuz. After struggling to attract foreign financing, Astana awarded GRES-3 to a Chinese-Kazakh consortium. Construction of GRES-3 has yet to begin. The Ministry of Energy said the land has only recently been secured, while design and cost documentation are not expected before September 2026.

Grid Capacity and Deficits

The official capacity balance projects a 1.278-gigawatt surplus in 2027 before reserve requirements, but a 2.366-gigawatt capacity deficit once the required reserve is included. The capacity gap is forecast to narrow to 638 megawatts in 2029 before widening again. The government promises about 13 gigawatts of additional capacity nationwide by the end of 2029. The government's response itemized only around 3 gigawatts of projects due between 2026 and 2029. The government provided neither a figure for the anticipated surplus in 2027 and 2028, nor a contingency plan for construction delays.

Environmental and Social Impact

At full capacity, 'Data Center Valley' could require more than five million tonnes of coal annually. The project involves efficient clean supercritical coal-fired generation and pollution-control technologies that extract more electricity per tonne and can reduce sulfur dioxide, nitrogen oxides, and particulate pollution. The ministry provided no measurable reduction targets and did not mention carbon capture. Ekibastuz coal has a high ash content and low calorific value, requiring more coal to be burned to produce the same amount of energy. In early 2026, authorities identified a self-heating area in a waste pile in Ekibastuz that could release pollutants. The data centers are expected to consume 2,300 cubic meters of water a day, drawn from the Satpayev Canal fed by the Irtysh River. No environmental-impact assessment has been made public, and Firebird.ai did not respond to requests for comment.

Project: Data Center Valley Pavlodar · Kazakhstan · Under construction · $115 bn

Key facts

  • Initial 50-megawatt facility enters service in June 2027.
  • Full capacity consumption estimated at 8.8 terawatt-hours annually.
  • GRES-3 is a planned 2.6-gigawatt coal plant awarded to a Chinese-Kazakh consortium.
  • Bogatyr Komir plans to raise coal production to more than 56 million tonnes by 2032.
  • Data centers expected to consume 2,300 cubic meters of water daily.
  • No environmental-impact assessment has been made public.

All sources (1)

  1. Can Kazakhstan Power Its AI Ambitions?The Times Of Central Asia · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn