New Tashkent: Accelerated Metro Construction Plan

The new city on the eastern edge of Tashkent – put into context for European companies

· 5 Sources

Scroll
Construction & infrastructure5 Sources

Published · last updated · 22 Jun 2026 – 23 Jun 2026

Tashkent plans to accelerate the construction of two new metro lines, 'Technopark – New Tashkent' and 'Pushkin – TTZ', using a fast-track method. The Directorate for the Construction of New Tashkent serves as the sole customer, with work required to follow European urban planning norms. The first phase of the 'Technopark – New Tashkent' line is scheduled for launch in 2026, with full commissioning planned by September 1, 2028.

Project Scope and Methodology

The draft Cabinet resolution proposes building two new metro lines using an accelerated fast-track scheme that involves parallel design and construction. The 'Pushkin – TTZ' line will extend 11 kilometers with 10 stations and a depot, while the 'Technopark – New Tashkent' line will be 21 kilometers long with 9 stations and a depot. Construction work must be performed strictly in accordance with European urban planning norms and EU standards.

Timeline and Customer

The Directorate for the Construction of New Tashkent has been approved as the single customer for both projects. The first stage of the 'Technopark – New Tashkent' line is planned for completion in 2026, with full operation scheduled for September 1, 2028. The 'Pushkin – TTZ' line is also expected to be launched by the same completion date in September 2028.

Land Inventory and Compensation

Relevant departments, including the Cadastre Agency and local Khokimiyats, must inventory all land, buildings, and green spaces in the track-laying zone within one month. A targeted compensation plan for potential damage to individuals and legal entities will be prepared and submitted to the government within three months.

Traffic and Infrastructure Adjustments

The Ministry of Transport is developing detour routes to ensure uninterrupted traffic during the construction period.

Key facts

  • The 'Pushkin – TTZ' line is 11 km long with 10 stations and a depot.
  • The 'Technopark – New Tashkent' line is 21 km long with 9 stations and a depot.
  • The fast-track method allows for parallel design and construction to reduce project timelines.
  • The Directorate for the Construction of New Tashkent is the sole customer for both projects.
  • Full commissioning of the 'Technopark – New Tashkent' line is planned for September 1, 2028.
  • Control over the implementation is entrusted to Deputy Prime Minister Achilbay Ramatov and Ministers Ilkhom Makhkamov and Sherzod Khidayatov.

All sources (6)

  1. Tashkent to build two new metro lines using fast-track methodUzDaily.uz · · EN
  2. В Ташкенте две новые линии метро до Нового Ташкента и ТТЗ построят по ускоренной схемеUzNews.uz · · RU
  3. Две новые линии метро Ташкента предлагается построить ускоренным методомSpot.uz · · RU
  4. В Ташкенте ускорят строительство двух новых линий метроDaryo · · RU
  5. Две новые линии метро до Нового Ташкента и ТТЗ построят по ускоренной схеме fast-trackUzDaily.uz · · RU
  6. В Ташкенте в срочном порядке начнут строительство двух новых линий метроНовости Узбекистана — Upl.uz · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn