The Directorate for the Construction of New Tashkent signed a direct contract with Gold Step Invest for the construction of a transport interchange at the intersection of Noviy Uzbekiston Street and the 4R12 highway. The project, preliminarily estimated at 350 billion sums, involves building 6 km of highway, three underground passages, and one bridge.
Contract Details and Timeline
The parties signed the contract for 350 billion sums on December 6, with the document posted on the portal on December 27. The customer transfers an advance of 15% of the project cost, amounting to 52.5 billion sums, to the general contractor. The preliminary completion date for the works, including demolition of existing buildings if necessary, is set for December 31, 2023, while the payment schedule is planned until the end of December 2025. The final cost will be determined based on the actual work performed.
Project Scope and Management
According to the project approved by President Shavkat Mirziyoyev on November 18, the construction includes one overpass, three tunnels, four roundabouts, and additional roads. The first stage involves building three tunnels: two in the 'Tashkent - Bostanlyk' direction, where work has already started and completion is scheduled for May 2024, and one in the 'Parkent - Tashkent' direction. The second stage is scheduled to begin in November 2024 and be completed by May 2025. On December 14, the Directorate also signed a direct contract with Architects Engineers Planners Advisors for project management services for the construction of the main interchange, with a cost of 5.5 billion sums.
Leadership and Corporate Connections
The directorate is headed by Davronjon Kabiljanovich Adilov, who is also Deputy Minister of Construction and Housing and Communal Services. Adilov previously served as deputy director of Gold Step Invest. According to the state register of legal entities, the company's current founders are Khayrulla Nurillaevich Ismatov and Kabiljan Frazilovich Adilov; Gazeta.uz notes that the latter's first name and surname match the patronymic and surname of the head of the directorate. Gazeta.uz sent several inquiries on the matter.
Key facts
- Contract value: 350 billion sums (approx. $28.4 million).
- Advance payment: 52.5 billion sums (15% of project cost).
- Construction scope: 6 km of highway, 3 underground passages, 1 bridge, 1 overpass, 4 roundabouts.
- Project management services cost: 5.5 billion sums.
- Director of the Directorate: Davronjon Kabiljanovich Adilov.
- Current founders of Gold Step Invest: Khayrulla Nurilloevich Ismatov and Kabiljan Frazilevich Adilov.