Uzbekistan: Uzbekhydroenergo invests $265 million in eight hydropower projects

Investors, volumes and stages of the region's major projects – for European suppliers

· 2 Sources

Scroll
Energy Uzbekistan2 Sources

Published · last updated · 26 Feb 2026

State-owned JSC Uzbekhydroenergo plans investments of $264.41 million for 2026, a 12 percent increase over the previous year. The portfolio includes eight strategic projects with a total capacity of 1,504.8 MW and a current total project value of approximately $2.97 billion.

The 2026 investment program of JSC Uzbekhydroenergo allocates funds amounting to $264.41 million. Financing is split between the company's own funds of $135.41 million and foreign loans totaling $129 million. Of the foreign capital, $109.1 million is attracted as direct foreign investment, while $19.9 million is backed by a state guarantee.

The strategic portfolio comprises eight facilities with a combined capacity of 1,504.8 MW and an average annual output of 4,918.9 million kWh. The largest project is the Upper Pskem pumped-storage hydropower plant with 600 MW capacity and an annual production of 1,080 million kWh, scheduled for commissioning by 2028. Other new construction projects include the Pskem hydropower plant on the Pskem River (248 MW, completion by 2030) and the Narin cascade complex (228 MW, completion by 2028).

Parallel to new construction, modernization of existing facilities is underway. The upgrade of the Lower Bozsu cascade and the modernization of the Shakhrihan cascade are both set for completion by 2027. Additionally, construction of the Mullalak plant (140 MW, completion by 2028) and the Kishtut cascade on the Topalang River (80 MW, completion by 2029) is planned.

Project: Uzbekhydroenergo Hydropower Projects · Uzbekistan · Under construction · $264 m

Key facts

  • 2026 Investment Volume: $264.41 million (+12 %)
  • Total Project Capacity: 1,504.8 MW
  • Upper Pskem Commissioning: 2028
  • Pskem and Narin Completion: 2028–2030

All sources (2)

  1. «Узбекгидроэнерго» направит почти 265 млн. долларов на развитие гидроэнергетики в 2026 годуUzDaily · · RU
  2. Uzbekhydroenergo to Direct Nearly US$265 Million Toward Hydropower Development in 2026UzDaily.uz · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn