Uzbekistan's President Shavkat Mirziyoyev ordered the acceleration of high-voltage line construction and grid modernization during a meeting on February 23, 2026. The move addresses the fact that one-third of the main transmission lines are outdated, posing a risk that rising generation capacity cannot be absorbed by demand.
Status and need for modernization
According to a presentation by the Ministry of Energy, the length of main transmission lines (110–500 kV) in Uzbekistan is 12,500 km. Approximately 3,900 km, or 32%, require renewal. Of the 91 substations at this voltage level with a total capacity of 30,984 MVA, 24 (28%) are considered outdated. Over the past four years, 1,310 km of new lines were built and 9 substations (220 kV) commissioned, adding 9,348 MVA of capacity. Investments amounted to $803.4 million.
Concrete construction plans and targets until 2030
The president ordered the acceleration of the projects 'Tamarjan – Sughdiana', 'Syrdarya – Khalka', and 'Karakul – Nurabad' with a total length of 602 km. By 2030, the line 'Yangi Angren – Namangan' and the 'Namangan' substation are planned. In Tashkent, 75 km of high-voltage lines and five substations are to be built new, 69 km of networks and 18 substations modernized, and 638 km of low-voltage networks and 161 transformer points renewed. Integration with neighboring countries to improve supply in the Fergana Valley is also under review.
Implementation and efficiency improvement
Abdumalik Nazirov, Chairman of the Board of 'National Electric Networks of Uzbekistan', emphasized that the meeting precisely defined where energy losses occur and where efficiency measures are needed. A scientific approach will be used, with experts analyzing local conditions to reduce losses. Asrorjon Askarov from 'Regional Electric Networks' added that every kilowatt-hour will now be tracked to increase supply security and prevent voltage fluctuations during peak times.
Project: Modernization of main power grids · Uzbekistan · Financing · $200 m
Key facts
- 32% of main transmission lines (110–500 kV) require renewal
- 28% of substations (110–500 kV) are considered outdated
- Investment volume of the last four years: $803.4 million
- Planned line length of accelerated projects: 602 km
- Target year for line Yangi Angren – Namangan: 2030