Uzbekistan: Financing secured for solar park with storage in Samarkand and Bukhara

Investors, volumes and stages of the region's major projects – for European suppliers

· 3 Sources

Scroll
Energy Uzbekistan3 Sources

Published · last updated · 29 Oct 2025 – 31 Oct 2025

ACWA Power, Sumitomo Corporation and other partners have secured financing for a solar project in Uzbekistan with a volume of $1.45 billion. The project includes 1000 MW of photovoltaics and 1336 MWh of battery storage in the Samarkand and Bukhara regions.

Financing Structure and Participation

The financing of the project amounting to $1.45 billion has been secured through a consortium of international financial institutions and private banks. The Japan Bank for International Cooperation (JBIC) provides the largest share with a loan volume of $635 million. The Asian Development Bank (ADB) organizes a financing package of $140 million, consisting of 70 million from own funds, 10 million from the LEAP 2 fund, and 60 million as syndicated loans. Additionally, the ADB provides credit guarantees of up to $85 million to mitigate payment risks. Private banks such as Sumitomo Mitsui Banking Corporation and Norinchukin Bank participate under insurance coverage by the Japanese Export and Investment Insurance (NEXI).

Project Scope and Technical Data

The project involves the construction and operation of solar photovoltaic plants with a total capacity of 1000 megawatts and battery energy storage systems (BESS) with a capacity of 1336 megawatt-hours. The facilities are located in the Samarkand and Bukhara regions. The shares in the project companies are distributed as follows: ACWA Power holds 51 percent, Sumitomo Corporation holds approximately 20.2 percent, and the Japanese utilities Shikoku Electric Power (Yonden) and Chubu Electric Power each hold 14.4 percent. The generated electricity is intended to supply approximately 600,000 households annually.

Timeline and Market Integration

The commissioning of the first project phase, designated as Sazagan Solar 1, is scheduled for 2027, with the second phase (Sazagan Solar 2) expected in 2028. All generated electricity will be sold to the National Electric Grids of Uzbekistan under a 25-year power purchase agreement. The project is considered one of the largest deals in the renewable energy sector in Central Asia and supports the national goal of increasing the share of renewable energy in installed capacity to 54 percent by 2030.

Project: Samarkand and Bukhara Solar Park with Storage · Uzbekistan · Under construction · $1.4 bn

Key facts

  • Total financing volume: $1.45 billion
  • Installed solar capacity: 1000 megawatts
  • Battery storage capacity: 1336 megawatt-hours
  • Commissioning Phase 1: 2027
  • Commissioning Phase 2: 2028
  • Power purchase agreement duration: 25 years

All sources (3)

  1. Крупнейший в Узбекистане солнечный и аккумуляторный энергопроект получит $1,45 млрдГазета.uz · · RU
  2. В Узбекистане построят крупнейшие в Центральной Азии солнечные электростанции с накопителями энергии: АБР и партнеры подписали соглашениеyuz.uz · · RU
  3. ACWA привлекла более $1,5 млрд на проект солнечной электростанции мощностью 1 ГВтSpot.uz · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn