Energy

Tajikistan: Financing Delays at Rogun Dam

Investors, volumes and stages of the region's major projects – for European suppliers

· 5 Sources

Scroll
Energy Tajikistan5 Sources

Published · last updated · 26 Aug 2025 – 31 Aug 2025

The World Bank appears to be reconsidering its involvement in the construction of the Rogun Dam in Tajikistan. Media reports suggest that the disbursement of approved funds has been paused pending the submission of a viable financing and debt repayment plan. Tajik authorities emphasize the project's strategic importance and are actively seeking additional international investors.

Financing Pause by the World Bank

According to reports, the World Bank Board approved a $350 million development grant for the project in late 2024. However, the disbursement of these funds is currently suspended until Tajik authorities submit a plan for responsible debt servicing and demonstrate the commercial viability of the facility. Official comments from the World Bank are not available, but the Russian newspaper Nezavisimaya Gazeta reported on August 25, 2025, that the bank froze the funds until Dushanbe meets a number of conditions.

Criticism and Environmental Risks

The World Bank's decision faced substantial backlash from experts who label the project a "white elephant," as well as environmental activists. A report by the environmental group Rivers Without Boundaries warned of severe ecological damage and economic uncompetitiveness. The World Bank's Inspection Panel noted in April 2025 that full-scale electricity generation could reduce the flow of the Amu Darya by more than 25 percent, endangering the livelihoods of up to 10 million people in Uzbekistan and Turkmenistan.

Costs and Debt Burden

The total cost of the project is estimated at over $9 billion. Rating agency Standard & Poor’s characterizes the project as costly, crowding out other state expenditures. Completing the project would require an additional roughly $6.4 billion. The government negotiated financing packages with multilateral partners to cover about 50 percent of the funds needed for completion by 2035. Delays in unlocking these funds, particularly from the World Bank, are currently a concern.

Conditions from International Partners

The World Bank demands that the Tajik government develop a macroeconomically sound financing plan that excludes an excessive increase in public debt. Additionally, a reliable financial plan is required that forms a sustainable commercial model, including firm commitments from neighboring states to purchase the generated electricity. Tajik officials have been instructed to intensify cooperation with international donors.

Construction Status and Political Context

President Emomali Rahmon emphasized the strategic importance of the Rogun Hydroelectric Power Plant for Tajikistan's energy independence during his visit on August 27, 2025. Two of the six planned turbines are already operational, having generated 9.1 billion kilowatt-hours of electricity to date. The completion of the fourth turbine is scheduled for September 2027. Despite improved relations with Uzbekistan and signed electricity supply agreements, financial hurdles for the project's completion remain high.

Project: Rogun Dam · Tajikistan · Under construction · $9.0 bn

Key facts

  • World Bank approved $350 million grant in late 2024; disbursement currently suspended.
  • Total project cost estimated at over $9 billion.
  • Additional costs for completion by 2035: approx. $6.4 billion.
  • Two of six turbines are operational; fourth turbine scheduled for Sept. 2027.
  • Standard & Poor’s rates project as costly, crowding out other expenditures.
  • Environmental groups warn of 25% reduction in Amu Darya water flow.

All sources (14)

  1. World Bank seems to be having second thoughts about Tajikistan’s Rogun DamEurasianet · · EN
  2. На Рогунской ГЭС в Таджикистане заработал первый робот-сварщикАзия-Плюс · · RU
  3. Глава государства Эмомали Рахмон ознакомился с ходом строительных работ на плотине Рогунской ГЭСАМИТ "Ховар" · · RU
  4. Выступление Президента Республики Таджикистан, Лидера нации уважаемого Эмомали Рахмона на встрече со строителями Рогунской ГЭСАМИТ "Ховар" · · RU
  5. За 17 лет на строительство Рогунской ГЭС направлено более 48 миллиардов 100 миллионов сомониАМИТ "Ховар" · · RU
  6. Эмомали Рахмон проверил ход строительства на ключевых объектах Рогунской ГЭСAvesta.tj · · RU
  7. Эмомали Рахмон встретился с работниками Рогунской ГЭС и активом города Рогуна - Новости ТаджикистанаAvesta.tj · · RU
  8. Эмомали Рахмон ознакомился с ходом строительства Рогунской ГЭСAvesta.tj · · RU
  9. Премьер Таджикистана пообещал энергетическую независимость страны к августу 2027 годаАзия-Плюс · · RU
  10. Президент Таджикистана выразил благодарность строителям гидроэлектростанции «РогунАМИТ "Ховар" · · RU
  11. Эмомали Рахмон открыл новые автодороги в Рогуне и Раштской долинеAvesta.tj · · RU
  12. Рахмон призвал ускорить привлечение инвестиций для Рогунской ГЭС на фоне сообщений о задержке финансированияАзаттык Азия · · RU
  13. Рахмон поручил ускорить строительство Рогунской ГЭС и обеспечить качество работAvesta.tj · · RU
  14. «Рогун» будет не только Таджикистану служить, но и связь между народами региона крепитьАМИТ "Ховар" · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn