Uzbekistan is intensifying tungsten, gold, and uranium extraction. The Uzbekskiy Kombinat Tekhnologicheskikh Metallov (TKM) is developing a tungsten complex with a capacity of up to 1 million tons of ore annually. Concurrently, power and water infrastructure is being expanded in the Jizzakh Free Economic Zone.
Tungsten Production and TKM Strategy
The Uzbekskiy Kombinat Tekhnologicheskikh Metallov (TKM) is building a tungsten complex based on the Sarikul deposit in the Samarqand region. The planned capacity is up to 1 million tons of ore per year, utilizing both open-pit and underground mining methods. Production is expected to reach up to 4,000 tons of 65-percent tungsten concentrate annually, with an estimated mine life of 20 years. Engineering and technological planning is being handled by Australian firms AMC Consulting Pty Ltd and NewPro Consulting and Engineering Services Pty.
Presidential Directives and Uranium Projects
President Shavkat Mirziyoyev issued directives to strengthen raw material capacities during a Jizzakh Regional Council session on December 2, 2025. In addition to the tungsten project, investors are to be attracted to a gold-bearing site in Gallaorol. Geological exploration at the Farish lead-zinc deposit and the feasibility study for the Arnasay uranium project are designated as priorities. Uzbekistan aims to become one of the world's leading tungsten producers through new developments in Gallaorol and Nurabad.
Infrastructure in Jizzakh FEZ
The Jizzakh Free Economic Zone (FEZ) currently hosts 30 projects worth $510 million, providing employment for around 10,000 people. Additional projects valued at $540 million are being implemented at an accelerated pace. To meet industrial demand, the Ministry of Energy has ordered the construction of 40 km of high-voltage transmission lines and a 40 MW substation for the FEZ. The 2026 infrastructure development program allocates 100 billion UZS for the construction of wastewater treatment facilities.
Energy Supply and Future Outlook
Regional energy supply is being strengthened by new capacities. Following the launch of a 220 MW solar power plant by Masdar (UAE) in Gallaorol in 2022, an additional 200 MW is being developed with Chinese partners, with a further 300 MW planned for the following year. Additionally, 150 small and mini hydropower plants with a combined capacity of 30 MW are scheduled for commissioning. TKM plans to implement over 70 projects in critical minerals by 2028, with a total value of $1.6 billion.
Project: Sarikul Tungsten Complex and Jizzakh FEZ · Uzbekistan · Under construction · $1.6 bn
Key facts
- Tungsten complex: Capacity up to 1 million tons of ore/year, 4,000 tons of concentrate/year
- TKM project portfolio: 70+ projects by 2028, volume $1.6 billion
- Jizzakh FEZ: 30 ongoing projects ($510 million), 10,000 jobs
- FEZ infrastructure: 40 km high-voltage line, 40 MW substation, 100 billion UZS for wastewater treatment
- Energy: Additional 200 MW (China) and 300 MW (planned), plus 30 MW hydropower