Uzbekistan plans to build three pumped-storage power plants (PSPP) with a total capacity of 1,400 MW by 2032. The projects will be implemented under a public-private partnership, with direct foreign investments playing a central role. Construction is scheduled to begin in 2027.
Legal Basis and Project Scope
The legal basis for the projects was established by Presidential Decree No. PP-163 on May 1, 2026. It outlines measures for modernizing the hydropower sector and introducing pumped-storage technologies in line with international standards. By 2032, three large PSPPs are to be built to enhance national grid stability and integrate renewable energy sources.
Locations, Capacities, and Costs
The "Khujakent" PSPP in Bustanlyk district (Tashkent region) has a capacity of 600 MW and is estimated to cost approx. $880 million. The "Aydarkul" PSPP in Farish district (Jizzakh region) covers 300 MW with estimated costs of $300.6 million. The "Karateren" PSPP in Takhtakupyr district (Republic of Karakalpakstan) provides 500 MW and costs approx. $550.2 million. Combined annual generation is projected at 2.7332 billion kWh.
Financing and Timeline
Financing will come from Uzbekhydroenergo JSC's own funds and direct foreign investment. $814 million in foreign capital is planned for Khujakent, $278.1 million for Aydarkul, and $508.9 million for Karateren. Technical and economic feasibility studies for all three sites are complete. Construction is scheduled to begin in 2027, while negotiations with foreign investors are currently ongoing.
Strategic Significance
In addition to the PSPPs, the decree provides for expanding general hydro capacity by 3,266 MW, raising total potential to 5,668 MW by 2032. Uzbekhydroenergo JSC is expected to transform from a pure producer into a modern system operator managing grid stability and capacity regulation. Pumped-storage plants serve as "natural batteries" with an efficiency of 70–85 % and can deliver full power within minutes.
Project: Khujakent, Aydarkul, Karateren Pumped-Storage Plants · Uzbekistan · Agreed · $1.7 bn
Key facts
- Total capacity of the three PSPPs: 1,400 MW
- Estimated total costs: approx. $1,730.8 million
- Planned construction start: 2027
- Legal basis: Presidential Decree No. PP-163 of May 1, 2026
- Annual generation: 2.7332 billion kWh
- Actor: Uzbekhydroenergo JSC