Uzbekistan and Russia signed a contract in May 2024 for the construction of a small nuclear power plant (330 MW) in the Jizzakh region. Rosatom is the general contractor, with commissioning planned for 2033. Negotiations are ongoing for a large reactor, with a contract expected by the end of 2025.
Contract for small nuclear power plant
In May 2024, the Uzbek company Uzatom and the Russian state corporation Rosatom signed a contract for the construction of a small modular nuclear power plant in the Jizzakh region. The project includes six RITM-200N reactors with a total capacity of 330 MW. Rosatom acts as the general contractor and is expected to involve local companies in construction. Financing is provided through foreign and local banks.
Timeline and location
Construction works at the site near Lake Tuzkan began in July 2024. The first reactor is scheduled to start operations by the end of 2029, with the remaining five reactors coming online at six-month intervals. Full commissioning is expected by 2033. Dry cooling towers will be used as the cooling technology to minimize water consumption given climatic conditions and projected water scarcity.
Plans for large nuclear power plant
Interest in a large nuclear power plant remains. Originally, a project with two WWER-1200 reactors with a total capacity of 2.4 GW and a planned commissioning by 2028 was discussed. Costs were estimated at around $11 billion. A contract for the large station is expected to be signed by the end of 2025. The first reactor of the large plant could likely begin operations around 2040.
Background and international cooperation
Cooperation between Uzbekistan and Russia in nuclear energy dates back to 2017. Since 2020, the partnership has initially focused on small modules. Uzatom has also signed cooperation agreements with the French company Assystem, the Chinese CNNC Overseas Ltd., and the World Nuclear Association. For the fuel cycle, Uzbek uranium ore will be used, enriched and fabricated into fuel elements in Russia, with spent fuel also returned to Russia.
Project: High-capacity nuclear power plant Uzbekistan · Uzbekistan · Under construction · $9.5 bn
Key facts
- Contract signing: May 2024
- Construction start: July 2024
- Capacity: 330 MW (6 x 55 MW)
- Reactor type: RITM-200N
- First reactor commissioning: End of 2029
- Full commissioning: 2033
- Location: Jizzakh region, Lake Tuzkan
- Large NPP contract: planned by end of 2025