Construction has begun on two waste-to-energy plants in the Uzbek regions of Samarkand and Andijan. The projects, with a total volume of $290 million, are being implemented by Chinese companies. The facilities are expected to generate 480 million kilowatt-hours of electricity annually and improve waste disposal.
Construction start in Samarkand
On July 18, 2025, the groundbreaking ceremony for a waste thermal treatment facility took place in the Navruz mahalla of the village of Xushrav in Samarkand. The project is being implemented by the Chinese company Shanghai SUS Environment LLC, which signed an agreement with the Agency for Waste Management and Circular Economy Development under the Ministry of Ecology of Uzbekistan. The investment volume is $150 million. Construction is taking place on a 15-hectare site based on Presidential Decree No. PQ-118 dated March 24, 2025.
Start in Andijan
At the same time, construction began on July 7, 2025, in the Xojobod district of the Andijan region for another facility. This project, valued at $140 million, is being carried out in cooperation with the Chinese company CAMC Engineering, with which a Memorandum of Understanding was signed in 2024. Completion is scheduled for 2028, corresponding to a construction period of approximately one and a half years.
Capacities and power sales
Both facilities are designed with identical technical specifications and are to process 1,500 tons of municipal solid waste daily. The annual electricity production per facility is 240 million kilowatt-hours. In Samarkand, the generated electricity will be sold to the joint-stock company „Uzenergosotish“ for a period of 30 years. The supply of waste is ensured through existing agreements. In total, the projects are expected to create between 250 and 300 new jobs.
Project: Waste-to-Energy Plants Samarkand and Andijan · Uzbekistan · Under construction · $290 m
Key facts
- Total volume of the two projects: $290 million
- Daily waste processing: 1,500 tons per facility
- Annual electricity production: 240 million kWh per facility
- Construction period Samarkand: 2025 to 2027
- Construction period Andijan: until 2028
- Power sales duration: 30 years to „Uzenergosotish“
All sources (6)
- Новый мусоросжигательный завод в Андижанской области будет перерабатывать 1500 тонн отходов в день и производить 240 млн кВт·ч энергии в годGazeta.uz (Telegram) · · RU
- В Андижанской области начали строить мусоросжигательный заводGazeta.uz · · RU
- Andijan region launches $140M waste-to-energy facility constructionKun.uz · · EN
- В Самарканде стартовало строительство завода по сжиганию отходовUzDaily (Telegram) · · RU
- В Самарканде стартовало строительство завода по сжиганию отходовUzDaily · · RU
- В Самарканде стартовало строительство завода по сжиганию отходовift.tt · · RU