Construction & cities

Uzbekistan: Construction start of nuclear power plant complex in Jizzakh

Investors, volumes and stages of the region's major projects – for European suppliers

· 3 Sources

Scroll
Construction & cities Uzbekistan3 Sources

Published · last updated · 26 Nov 2025 – 2 Dec 2025

Excavation work has begun in Uzbekistan for the country's first nuclear power plant. The project in the Jizzakh region combines two large VVER-1000 reactors with two small modular RITM-200N reactors. Total capacity is set at 2110 MW.

Construction start and technical configuration

Excavation work for the reactor building foundations began in October 2025 in the Jizzakh region. The plant will comprise two large VVER-1000 reactors with 1 GW each and two small modular reactors (SMR) of the RITM-200N type with 55 MW each. Total capacity is 2110 MW. First concrete pouring for the SMR unit is scheduled for March 2026, with first criticality expected by late 2029.

Project development and partnership

The project was initially planned as a pure SMR facility with six units. In September 2025, an agreement between Uzbekistan and Russia expanded the scope to include large reactors. The general contractor is the Russian state corporation Rosatom via its subsidiary Atomstroyekspert. Estimated total costs do not exceed $1 billion.

Infrastructure and employment

Approximately 1.5 million cubic meters of soil will be excavated, with temporary housing for construction workers already being built. Plans are underway for a mono-city for 10,000 residents located 16 km from the site. Up to 13,000 jobs are expected during construction and up to 2,000 during operation. Annual electricity generation is projected at 16 to 17 billion kWh.

Project: High-capacity nuclear power plant Uzbekistan · Uzbekistan · Under construction · $9.5 bn

Key facts

  • Excavation start: October 2025
  • Total capacity: 2110 MW
  • Reactor types: 2x VVER-1000, 2x RITM-200N
  • Volume: max. $1 billion
  • First concrete (SMR): March 2026
  • Jobs (construction): up to 13,000

All sources (3)

  1. Слушания по строительству АЭС в Узбекистане назначены на 23 декабряГазета.uz · · RU
  2. Uzbekistan progressing work on first nuclear power plantWorld Nuclear News · · EN
  3. Uzbekistan progressing work on first nuclear power plantworld-nuclear-news.org · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn