Uzbekistan: Construction start of copper smelter and launch of MOF-3 at Almalik complex

Investors, volumes and stages of the region's major projects – for European suppliers

· 4 Sources

Scroll
Mining & metals Uzbekistan4 Sources

Published · last updated · 16 Mar 2026 – 24 Mar 2026

Construction has begun on a new $2.5 billion copper smelter at the Almalik Mining and Metallurgical Combine (AGMK) in Uzbekistan. Simultaneously, the third copper concentration plant (MOF-3) was launched. President Shavkat Mirziyoyev ordered the acceleration of further projects and the reduction of costs for the fourth concentration plant (MOF-4).

Commissioning and Construction Start

On March 16, 2026, the third copper concentration plant (MOF-3) at the Almalik Mining and Metallurgical Combine (AGMK) was commissioned. The foundation stone for this facility was laid on July 29, 2021. Concurrently, construction began on a new copper smelter, which serves as a technological continuation of the project and is estimated to cost $2.5 billion. These measures are expected to increase annual copper cathode production from 148,500 to 300,000 tons.

Production Targets and Capacities

With the launch of MOF-3 and the new smelter, annual gold production will rise from 20 to 33 tons, silver from 161 to 203 tons, and molybdenum from 850 to 1,700 tons. The capacity of MOF-3 is expected to double daily copper concentrate output from 2,400 to 5,000 tons upon full operation. The total cost of the MOF-3 project reached $5.3 billion, with construction costs for the plant itself amounting to $2.7 billion.

Plans for MOF-4 and Cost Optimization

President Shavkat Mirziyoyev indicated that construction costs for the fourth copper concentration plant (MOF-4) could be reduced from the initial $2.7 billion to approximately $2 billion. By leveraging domestic patents and technologies, costs might be lowered further to around $700 million. International companies are to be engaged in preparing the technical feasibility study for MOF-4, with water supply and infrastructure issues taking priority.

Strategic Goals by 2030

By 2030, extraction volumes in Uzbekistan are targeted for significant increases: gold to 175 tons, silver to 500 tons, uranium to 15,000 tons, and copper to 500,000 tons. In 2026, 90 projects with an investment volume of $2.2 billion are planned for the sector. Overall, projects valued at $22 billion are expected to create up to 40,000 new jobs, including 7,500 engineers.

Project: Copper Smelter and MOF-3/4 at AGMK · Uzbekistan · Under construction · $2.0 bn

Key facts

  • Construction start of copper smelter on March 16, 2026
  • Investment volume of smelter: $2.5 billion
  • Commissioning of copper concentration plant 3 (MOF-3)
  • Total costs for MOF-3: $5.3 billion
  • Planned cost reduction for MOF-4 to approx. $2 billion
  • Target copper production by 2030: 500,000 tons
  • Planned jobs from projects worth $22 billion: 40,000

All sources (6)

  1. На АГМК началось строительство нового медеплавильного завода за $2,5 млрдSpot (Telegram) · · RU
  2. Мирзиёев поручил АГМК ускорить проекты МОФ-3 и нового медеплавильного заводаSpot (Telegram) · · RU
  3. Мирзиёев поручил АГМК ускорить проекты МОФ-3 и нового медеплавильного заводаSpot · · RU
  4. Узбекистан может войти в тройку крупнейших производителей меди в миреDaryo · · RU
  5. Президент поручил ускорить проекты в металлургии, НГМК расширит золотой рудник «Мурунтау»Газета.uz · · RU
  6. Стоимость строительства медно-обогатительной фабрики №4 можно снизить до $2 млрд — президентГазета.uz · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn