Uzbekistan is building eleven waste-to-energy plants across six regions. The first six projects, valued at $933 million, will process 3.6 million tons of waste annually and generate 1.6 billion kilowatt-hours of electricity. A second phase involving five additional plants costs $633 million.
Construction Projects and Capacities
According to the Agency for Waste Management and Circular Economy Development, six new waste-to-energy plants are being constructed in the Andijan, Namangan, Fergana, Samarkand, Kashkadarya, and Tashkent regions. The total cost for these six projects is $933 million. The facilities are designed to process up to 3.6 million tons of waste annually and generate approximately 1.6 billion kilowatt-hours of electricity. Concurrently, construction has begun on five additional plants with an investment volume of $633 million.
Commissioning and Infrastructure
A key project is the plant in Samarkand, scheduled for commissioning in early 2027. It will process up to 1,500 tons of waste daily and produce 240 million kilowatt-hours of electricity annually. To support waste logistics, 28 transfer stations are to be built in 2026, increasing to 70 by 2030. Additionally, the number of landfills will be reduced by 32.6 percent by 2026 and by half by 2030; 18 existing landfills are to be reclaimed.
Market Status and Challenges
Currently, 64 percent of the population, or 23.9 million people, use waste disposal services; the target for the end of 2026 is 90 percent. Outstanding consumer debts exceed 622.7 billion sum. In 2025, more than 10,000 cases of illegal waste dumping were identified, with a further 2,107 violations recorded in the first quarter of 2026. A persistent challenge remains plastic disposal, as plastic accounts for over 10 percent of waste, yet processing capacities are still insufficient.
Project: Waste-to-Energy Plants Uzbekistan · Uzbekistan · Under construction · $1.6 bn
Key facts
- Construction of 11 waste-to-energy plants in 6 regions
- Cost for the first 6 plants: $933 million
- Cost for another 5 plants: $633 million
- Annual waste processing: up to 3.6 million tons
- Annual electricity generation: approx. 1.6 billion kWh
- Samarkand commissioning: early 2027