The construction cost of Uzbekistan's first toll road connecting Urgench and Khiva has increased to $150 million, which is $30 million or 25% higher than the initial estimate of $120 million. Anvar Davletov announced the final cost at the launch ceremony in the presence of President Shavkat Mirziyoyev.
The Committee on Highways confirmed that the initial project cost was $120 million, but the current total cost has risen by $30 million. Construction works were carried out in parallel with the design phase, a factor noted as carrying risks for adjustments. The customer is the Directorate under the Committee for Automobile Roads of the Ministry of Transport, and contractors are organizations subordinate to the committee. An open tender for the project was not held.
The first toll section of the Urgench–Khiva highway is 35 km long and includes one underground tunnel, eight overpasses, 15 bridges, and 106 culverts.
Project: Urgench–Khiva Highway · Uzbekistan · In operation · $150 m
Key facts
- The final cost of the Urgench-Khiva toll road is $150 million.
- The cost increase of $30 million represents a 25% rise over the initial $120 million estimate.
- The highway is 35 km long and reduces travel time between Urgench and Khiva.
- Construction began in February with concurrent design and engineering work.
- No open tender was held for the project.
- The foreign partner for financing has not yet been determined, though negotiations are ongoing.
All sources (6)
- President Shavkat Mirziyoyev inspects new transport infrastructure connecting Urgench and Khivapresident.uz · · EN
- Uzbekistan launches construction of first toll road linking Urgench and KhivaKun.uz · · EN
- Стоимость строительства первой платной автомобильной дороги Узбекистана Ургенч — Хива выросла до $150 млнGazeta.uz (Telegram) · · RU
- Первая платная дорога в Узбекистане обошлась на $30 млн дороже первоначальной оценкиKun.uz (Telegram) · · RU
- Первая платная дорога в Узбекистане обошлась на $30 млн дороже первоначальной оценкиKun.uz · · RU
- Cost of Urgench-Khiva Toll Road Rises to US$150 MillionUzDaily · · EN