The 1-GW solar project in Uzbekistan is fully operational. Energy China has realized two 500-MW farms in the Bukhara and Kashkadarya regions, with the final capacity commissioned in June 2024.
Project Realization and Timeline
Energy China has completed the 1-GW solar project in Uzbekistan. The facility consists of two 500-MW solar farms in the Bukhara and Kashkadarya regions, developed largely in parallel. The first 400 MW entered commercial operation in December 2023, with the remaining 600 MW commissioned in June 2024. Energy China acted as developer and sponsor, coordinating design, engineering, procurement, and construction via a wholly owned local project company.
Financing and Structure
The project utilizes RMB-denominated financing of 3.3 billion RMB over 15 years, backed by Sinosure. Energy China provided $410 million in equity. Repayment is underpinned by a 25-year power purchase agreement (PPA) with the state-owned company JSC Uzenergosotish. Sinosure insurance covers 95% of political and commercial risks.
Impact and Background
The facility generates an estimated 2,400 GWh of solar electricity annually, representing about 32% of Uzbekistan's 2023 consumption. This avoids 2.4 million tonnes of CO2 and reduces gas usage by roughly 520 million cubic metres per year. The project is part of a memorandum of understanding signed in 2023 to develop a total of 2 GW of solar power in Uzbekistan.
Project: Energy China 1 GW solar project (Bukhara and Kashkadarya) · Uzbekistan · In operation
Key facts
- Capacity: 1 GW (two 500-MW farms)
- Locations: Bukhara and Kashkadarya regions
- Commissioning: December 2023 (400 MW), June 2024 (600 MW)
- Equity: $410 million
- Debt volume: 3.3 billion RMB
- Annual generation: 2,400 GWh