President Shavkat Mirziyoyev announced on July 27 that an incorrect site selection for a gas-fired power plant in the Surkhandarya region will require an additional $300 million for gas connection. The President ordered a review of the contract terms after criticizing officials for not studying the agreement with the project initiator carefully enough.
The project likely refers to a 1.6 GW gas-fired power plant in the Angor district implemented by 'SCE-Quvvat', with Chinese company 'POWERCHINA' as the general contractor. In June 2023, the Ministry of Energy reported that the Asian Infrastructure Investment Bank and the Islamic Development Bank would invest €325 million in the construction without state guarantees. The facility is designed to operate with 63% efficiency using latest technologies, expected to save 1.1 billion cubic meters of natural gas annually.
Project: Surkhandarya gas power plant · Uzbekistan · Under construction
Key facts
- President Shavkat Mirziyoyev made the announcement on July 27.
- The error in site selection necessitates an extra $300 million for connecting gas to the facility.
- Officials were criticized for insufficiently studying the contract terms with the project initiator.
- The project is a 1.6 GW gas-fired power plant in the Angor district.