Uzbekistan loses 1,600 MW of generation capacity in outage

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
Energy Uzbekistan1 Source

Published · last updated · 25 Sep 2026

An emergency outage of 1,600 MW occurred at a new thermal power plant owned by EDF in the Syrdarya region of Uzbekistan on 25 September. The incident temporarily disrupted electricity supplies, mainly affecting agricultural water pumps and residential consumers, before reserves restored normal power.

The outage happened at 05:05 during commissioning and testing work at the recently built plant. Kazakhstan's KEGOC reported a 1,516 MW generation outage in Uzbekistan's power system at 05:02, which caused power flow from the Central Asian power system and separated transit along the North-South direction. In Kazakhstan, consumer restrictions reached 962 MW, but emergency protection systems operated as designed. Parallel operation between the Southern Zone of Kazakhstan's Unified Power System and the Central Asian Unified Power System was restored at 05:43, leading to the lifting of restrictions. KEGOC confirmed the Uzbek side's information about the emergency loss of generation capacity at the EDF plant in the Syrdarya region.

Project: EDF thermal power plant in Syrdarya · Uzbekistan · Under construction

Key facts

  • The outage occurred at 05:05 on 25 September.
  • The plant is owned by EDF and located in the Syrdarya region.
  • Disruptions mainly affected pumps for agricultural water supply and residential consumers.
  • Reserve capacity from energy storage systems and power plants was used to restore supplies.

All sources (1)

  1. Uzbekistan loses 1,600 MW of generation capacity in outageUzDaily · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn