In May 2012, the TAPI project for delivering natural gas from Turkmenistan to Afghanistan, Pakistan, and India made significant progress with the signing of purchase agreements by India and Pakistan.
Project Milestones and Agreements
The TAPI project began in 2002, with the Asian Development Bank (ADB) allocating $1 million for the feasibility study. The first phase was officially completed in December 2010 with the signing of all project agreements by participating countries. The second phase, scheduled to end in 2012, concluded with the successful signing of sales agreements in May 2012.
Technical and Financial Structure
The 1800 km pipeline will be laid from the gas fields of southeastern Turkmenistan to intake points in Afghanistan, Pakistan, and India.
Project: TAPI gas pipeline · Central Asia (regional) · Under construction · $10 bn
Key facts
- The TAPI pipeline is 1800 km long.
- The project cost is approximately $7.6 billion.
- Pakistan, India, and Afghanistan committed to taking 33, 25, and 5 billion cubic meters/year respectively by 2016.
- The ADB allocated $1.5 million for the third phase of the TAPI project.
- The first ADB loan to Turkmenistan for the North-South railway project was $125 million.