Turkmenistan is advancing TAPI pipeline and infrastructure projects in Herat

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
EnergyCentral Asia (regional)1 Source

Published · last updated · 16 Sep 2026

By mid-September, 122.3 kilometers of pipe had been welded and laid along the TAPI route in Herat Province, with 71.5 kilometers buried and 33 kilometers undergoing hydrostatic testing. Afghanistan’s Ministry of Mines and Petroleum reported that 150.3 kilometers of the 153-kilometer route in the province had been prepared for installation as of September 15. Work on Afghan territory resumed in September 2024.

The TAPI pipeline is designed to run roughly 1,814 kilometers from Turkmenistan’s Galkynysh gas field through Afghanistan and Pakistan to the Indian border. Its planned capacity is 33 billion cubic meters a year, with allocations of 5% for Afghanistan and 47.5% each for Pakistan and India at full capacity. In August, Turkmengaz and Afghan Gas signed a memorandum on the gasification of the province. Abdul Ghani Baradar proposed a long-term contract and flexible pricing, but no contract has been signed and neither volumes nor a start date have been agreed.

On September 15, representatives of Da Afghanistan Breshna Sherkat and a Turkmen technical delegation discussed specifications and the Nur-ul-Jihad substation. Work on the first 22-kilometer section toward Sanabar began in 2024, while the full line to Herat would run for about 120 kilometers. On September 16, Herat Governor Noor Ahmad Islamjar and Turkmen Consul General Batyr Yolov discussed rail links, trade, and electricity supplies. The talks confirmed continued interest in the route but produced no new construction figures.

Project: TAPI gas pipeline · Central Asia (regional) · Under construction · $10 bn

Key facts

  • 122.3 km of pipe laid in Herat Province by mid-September.
  • 150.3 km of the 153 km route prepared for installation.
  • 71.5 km of pipe buried; 33 km completed hydrostatic testing.
  • Pipeline capacity planned at 33 billion cubic meters per year.
  • No contract signed; volumes and start date not agreed.
  • No completion date announced publicly.

All sources (1)

  1. Turkmenistan Advances TAPI Pipeline and Infrastructure Projects in HeratThe Times Of Central Asia · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn