Turkmenistan has received over 35,000 meters of steel pipes for the TAPI gas pipeline from Saudi Arabia, financed by a $40 million contract. The first batch of approximately 4,956 meters arrived at the Mary region, with transportation and installation ongoing. The delivery of materials for the Turkmen section marks the first official report of construction material supplies for the project.
On November 19, Turkmengaz announced a contract with Saudi Arabia's Global Pipe Company for the supply of steel pipes. The Saudi Fund for Development is financing the $40 million contract. Pipes are being delivered by sea from Dammam port through the Caspian Sea to the International Port of Turkmenbashi. More than 35,000 meters of steel pipes will be delivered in two stages.
Construction of the Turkmen section began in 2015 and was claimed to be completed in February 2018. In February 2018, the government stated that the 244-kilometer section from the Galkynysh gas field to the Afghan border was finished. Transportation to construction sites and installation of these pipes is currently ongoing. The pipeline is planned to deliver 33 billion cubic meters of gas annually to Pakistan and India.
Project: TAPI gas pipeline · Central Asia (regional) · Under construction · $10 bn
Key facts
- The total length of the TAPI pipeline is 1,814 kilometers.
- The Turkmen section is 214 kilometers long, while 744 kilometers are planned for Afghanistan.
- Only 35 kilometers of pipes are being supplied for the 214-kilometer Turkmen section.
- The project cost was reduced from $10 billion to $7 billion.
- Construction of the Afghan section started on February 23, 2018.
- Turkmenistan initially allocated over $45 million in June 2016 for the initial stage.