According to Reuters, citing Turkmen officials, Turkmenistan has welded and laid about 124 km of pipe on the 153 km Afghan section of the TAPI gas pipeline from Serhetabat to Herat. The section is to be completed by the end of 2026, and first gas is to flow to Herat in early 2027. For now, Turkmenistan is building the pipeline with its own funds.
The 214 km Turkmen section of the pipeline was completed in 2024, and pipe laying towards Herat began in September of the same year. The Herat section makes up less than a tenth of the entire 1814 km route, which is to reach Pakistan and India. Turkmenistan ranks fourth in the world in gas reserves, but almost all of its exports currently go to China.
According to Afghan media, the Herat section will cost about $600 million. Initially, Afghanistan is to buy about 500 million cubic metres of gas per year, while the pipeline's capacity is 33 billion cubic metres. Afghanistan's state gas company signed a preliminary agreement in August to buy gas for Herat; the price was not disclosed.
Muhammedmurat Amanov, head of TAPI Pipeline Company Limited, said the section to Herat should generate the first revenues and strengthen lenders' confidence. He expects to raise funds for the project from the Asian Development Bank and the Islamic Development Bank. The Asian Development Bank said it suspended regular assistance to Afghanistan after the Taliban came to power in 2021 but remains involved in TAPI, and that a financing decision will depend on circumstances.
Experts estimate the cost of the entire TAPI project at about $10 billion. Analysts and investors describe the project as difficult: the Taliban government is not officially recognised by anyone, relations between India and Pakistan remain tense, and separatists have long been active in Pakistan's Balochistan, through which the pipeline is to pass. Pakistan's ambassador to Turkmenistan, Farial Legari, gave assurances that Islamabad remains interested in TAPI.
Project: TAPI gas pipeline · Central Asia (regional) · Under construction · $10 bn
Key facts
- Serhetabat–Herat section: about 124 of 153 km welded and laid
- Completion planned by the end of 2026, first gas to Herat in early 2027
- Cost of the Herat section: about $600 million (Afghan media)
- Initial offtake about 500 million cubic metres of gas per year, pipeline capacity 33 billion cubic metres