Energy

Tajikistan: Rogun HPP Construction Faces Pandemic and Funding Delays

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
Energy Tajikistan1 Source

This summary was written by an AI.

Published · last updated · 14 May 2020

The coronavirus pandemic has slowed construction at the 'Rogun' HPP by freezing work pace, although no virus cases have been detected among workers. The Tajik government acknowledges a budget damage of $384 million due to the crisis, with remittances dropping significantly. According to the approved plan, the Rogun HPP is to be fully commissioned in 2029.

Impact of the Pandemic on Construction

The virus has not been detected in workers, but it has frozen the pace of work, slowing down the construction process. Work volumes have decreased, with only work on the units continuing, while dam construction work must continue. Several Italian engineers who arrived in December are stuck in the country due to temporary restrictions on air traffic. The Italian company Salini Impregilo stated that work at the station is continuing.

Financial Challenges and Budget Impact

Emomali Rahmon admitted that the crisis associated with the coronavirus has already caused damage to the country's budget in the amount of $384 million. Remittances, on which the country's economy strongly depends, decreased in March and the first half of April by 80 million, or twice compared to the same period in 2019. An obvious lack of funds to continue work forced the authorities to exempt the company 'Tractebel Engineering S.A.' from paying a large tax to the budget on May 5. Last year, the government of Tajikistan spent $250 million on the construction of the HPP. To continue the construction of Rogun in 2017, state 'eurobonds' in the amount of $500 million were sold.

Future Risks and Financing Plans

Anatoly Kolesnichenko says that huge funds are needed to launch the remaining HPP units, but there is no such money in Tajikistan and it is impossible to borrow such money from others. Filippo states that the biggest risk lies in the lack of investment to fulfill financial obligations to Salini Impregilo. In a letter to the IMF, Emomali Rahmon stated that authorities are making every attempt to continue financing the construction of the HPP this year at the planned level. The government states that it will take 'preferential' loans only in cases of acute necessity and will make efforts to find necessary financial resources without increasing the country's external debt. If restrictions on citizen movement are announced, it will affect the construction of the HPP. The launch of the third unit of the Rogun HPP, which is planned for 2024, may be delayed due to the coronavirus pandemic.

Project: Rogun HPP · Tajikistan · Under construction · $6.4 bn

Key facts

  • The Rogun HPP is to be fully commissioned in 2029 according to the approved plan.
  • The Government of Tajikistan signed a contract with Salini Impregilo in 2016 for $3.9 billion.
  • Two HPP units have already been commissioned, with four more to be installed.
  • The capacity of the 6 units will be 3600 megawatts, generating more than 17 billion kilowatt-hours of electricity per year.
  • More than 800 infections with the new coronavirus have been officially registered in Tajikistan.

All sources (1)

  1. Пандемия повлияла на темпы строительства Рогунской ГЭС?Азаттык Азия · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn