Energy

Tajikistan: Government secures additional funding for Rogun HPP completion

Investors, volumes and stages of the region's major projects – for European suppliers

· 1 Source

Scroll
Energy Tajikistan1 Source

Published · last updated · 30 Sep 2024

The Government of Tajikistan has attracted an additional $1.15 billion for the completion of the 'Rogun' hydroelectric power station, with negotiations for a $650 million grant from the World Bank nearing conclusion. President Emomali Rahmon announced the funding details during a meeting with plant builders, noting that loan agreements with the Asian Infrastructure Investment Bank are also at a final stage.

Agreements for preferential lending have already been signed with the Islamic Development Bank for $150 million and the Saudi Fund for Development for $100 million. Other Arab development funds, including the OPEC Fund for International Development, Kuwait Fund for Arab Economic Development, Abu Dhabi Fund, and the Italian Savings and Trust Fund, have decided to allocate $100 million each.

Approximately 12 years after the start of resettlement from the flooding zone, 3,212 families have been relocated from the Nurek district and the city of Rogun. These families were resettled to the cities and districts of Dangara, Rudaki, Fayzabad, Tursunzade, Rogun, and Nurek, where they were provided with new permanent housing and household plots of land. Other measures for preparing the flooding zone include the relocation of power lines, dismantling of substations, communication lines, and roads. Issues regarding the relocation of roads from the flooded zone of the right bank to the territory of the city of Rogun and the Nurek district are being resolved within the framework of the construction of the 'Rogun - Obigarm - Nurek' road.

The installation of the next hydro unit is scheduled for autumn 2026, with dam raising to 1150 meters planned for August 2026 and to 1175 meters for August 2027. The Ministry of Finance is instructed to allocate funds in time for completed works, construction materials, equipment, and fuel. The Committee on Architecture and Construction must strengthen quality control and ensure timely state expertise of proposed projects. The Ministry of Transport is instructed to complete the construction project of the 'Rogun - Obigarm - Nurobod' road in time.

Project: Rogun HPP · Tajikistan · Under construction · $6.4 bn

Key facts

  • Additional funding of $1.15 billion secured for 'Rogun' HPP completion.
  • Negotiations with the World Bank for a $650 million grant are concluding.
  • Loan agreement negotiations with the Asian Infrastructure Investment Bank for $500 million are at the final stage.
  • 3,212 families have been resettled from the Nurek district and the city of Rogun.
  • Installation of the next hydro unit is scheduled for autumn 2026.
  • Construction of a 920-meter bridge over the reservoir must be accelerated.

All sources (1)

  1. Правительство Таджикистана привлекло еще $1,15 млрд на достройку Рогунской ГЭСАзия-Плюс · · RU

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn