Tajikistan has activated the first tranches of international financing agreements for the construction of the Rogun Hydropower Plant. The 2026 state budget allocates over $1 billion, supplemented by funds from the National Bank's reserve fund. The World Bank, AIIB, and Arab development funds are providing capital to accelerate the construction of the third unit by September 2027.
Activation of International Financing Agreements
The Government of Tajikistan has activated the first tranches of international financing agreements for the Rogun Hydropower Plant. Finance Minister Faiziddin Qahhorzoda confirmed on February 13, 2026, that all necessary conditions have been met to access the funds. The first tranche from the World Bank amounting to $350 million has already been disbursed. Negotiations for an additional $300 million from the World Bank have been successfully concluded, with disbursement expected by mid-2026. Furthermore, all procedures to secure $500 million from the Asian Infrastructure Investment Bank (AIIB) have been completed, with $270 million to be disbursed as the first tranche.
State Funds and Reserve Fund
For the year 2026, the Tajik government plans to allocate at least 10 billion Somoni (over $1 billion) for the project. Of this, 8.2 billion Somoni are already included in the state budget. Additionally, the lower house of parliament passed a law on January 22, 2026, allowing the use of 916 million Somoni (approx. $100 million) from the Reserve Fund of the National Bank of Tajikistan for the dam's construction. These funds are derived from the financial results of 2024. The total state budget for 2026 allocates 15 billion Somoni to the fuel and energy complex, with the majority directed towards the completion of the Rogun Hydropower Plant.
Further International Partners and Contract Signings
In addition to activated funds, further financing sources are being secured. The Abu Dhabi Fund for Development signed an agreement for $100 million on February 4, 2026, in Dubai, focusing on Lot 2 of the project, which covers the installation of hydroelectric equipment and the construction of the powerhouse. Further procedures to secure $150 million from the Islamic Development Bank, as well as $100 million each from the Saudi Fund for Development, the Kuwait Fund for Arab Economic Development, and the OPEC Fund for International Development, are in the final stages of tender procedures.
Construction Progress and Schedule
Construction of the Rogun Dam is approximately 60 percent complete. The dam has a height of 151 meters and reaches an elevation of 1116 meters above sea level. Two temporary units, commissioned in 2018 and 2019, have generated a total of 9.9 billion kilowatt-hours of electricity by the end of 2025. The commissioning of the third unit has been scheduled for September 2027. The launch of the final unit is expected in 2029. With an installed capacity of 3780 megawatts, the facility will become the largest hydropower plant in Central Asia upon completion.
Financing Gap and Total Costs
The estimated total cost for completing the Rogun Hydropower Plant ranges between $6.2 and $6.4 billion. Since 2008, over 48.1 billion Somoni have been invested from the state budget and other sources. The Tajik government has reached agreements with development partners for more than $2 billion. Rating agencies such as Standard & Poor's note that financing from partners like the World Bank depends on the fulfillment of remaining conditions. The government aims for energy independence by 2027 and seeks to reduce dependence on external loans by utilizing domestic resources and grants.
Project: Rogun HPP · Tajikistan · Under construction · $6.4 bn
Key facts
- 2026 State Budget: At least 10 billion Somoni (>$1 billion) allocated for the project.
- World Bank: First tranche of $350 million disbursed; additional $300 million expected by mid-2026.
- AIIB: $500 million approved, with $270 million as the first tranche.
- Abu Dhabi Fund for Development: $100 million agreement signed (Lot 2).
- Construction Progress: Approximately 60% complete; dam height 151 meters.
- Schedule: Third unit commissioning in September 2027; final unit in 2029.
- Reserve Fund: 916 million Somoni (~$100 million) released from the National Bank's reserve fund.
All sources (13)
- Таджикистан наращивает финансирование Рогуна за счет внутренних ресурсовАзия-Плюс · · RU
- Таджикистан направит резервы Нацбанка на достройку Рогунской ГЭСРитм Евразии · · RU
- Международные доноры приступают к финансированию Рогунского проектаАзия-Плюс · · RU
- Таджикистан привлёк $100 млн на строительство Рогунской ГЭСAvesta.tj · · RU
- Таджикистан привлек $100 млн от Фонда развития Абу-Даби на достройку Рогунской ГЭСФергана - международное агентство новостей · · RU
- Фонд развития Абу-Даби выделит $100 млн на энергетический проект в ТаджикистанеAnadolu Ajansı · · RU
- Таджикистан и Фонд развития Абу-Даби подписали соглашение о финансировании Рогунской ГЭСvecherka.tj · · RU
- Фонд развития Абу-Даби даст $100 млн на достройку Рогунской ГЭСАзия-Плюс · · RU
- На строительство Рогунской ГЭС в 2026 году запланировали направить свыше $1 млрдАзия-Плюс · · RU
- Эмомали Рахмон обсудил с главой АБИИ сотрудничество в сфере строительства и модернизации ГЭС в ТаджикистанеАзия-Плюс · · RU
- Таджикистан привлечет $1 млрд на строительство Рогунской ГЭСКазинформ · · RU
- Tajikistan Plans Over $1 Billion for Rogun Hydropower Project in 2026The Times Of Central Asia · · EN
- Рогунская ГЭС: масштабное финансирование на фоне критики по долгам, экологии и прозрачностиPamir Inside · · RU