Construction of the Silleno polyethylene plant in Kazakhstan's Atyrau region is more than 42% complete, according to General Director Mukhtar Avutbayev. The plant is designed for an annual capacity of 1.25 million tonnes of polyethylene. The first granules are planned for July 2029. About 40 Kazakh companies are involved, with contracts worth more than $1.2 billion already signed.
Construction status
According to Silleno General Director Mukhtar Avutbayev, the project is moving from the preparatory stage to active installation. More than 5,200 people and over 680 units of special machinery are currently working on the site. During the most intensive phase, the number of construction workers is to exceed 15,000. Avutbayev said that earlier stages focused mainly on design work and equipment orders, while construction and installation work is now in full swing.
Timeline and capacity
Construction runs from 2025 to 2028 inclusive, and the first polyethylene granules are scheduled for 2029. Installation is to be completed and commissioning started in 2028, with the plant to enter operation in 2029. The planned annual capacity is 1.25 million tonnes of polyethylene. The company estimates that the complex will account for about 1% of global polyethylene production and that its design capacity will exceed the combined capacity of similar plants in Uzbekistan, Turkmenistan and Azerbaijan.
Process chain
Ethane will first be separated from dry gas from the Tengiz field in a gas separation complex, with the plant requiring up to 1.6 million tonnes of this feedstock per year. The ethane will then be fed to a pyrolysis unit to produce ethylene, which is converted into polyethylene. Denis Kozyrev, director of a department in Silleno's operations unit, said the plant's six pyrolysis furnaces differ from equipment used simply to heat petroleum products. According to Kozyrev, the reaction takes about one tenth of a second at temperatures of up to 850 degrees. Quench-evaporation equipment in the furnace cools the pyrolysis gas from 850 to 500 degrees and, in a second stage, to 250–300 degrees.
Kazakh suppliers
One of the largest items on site is a fractionation column 101.8 metres high and 7.5 metres in diameter, weighing about 1,500 tonnes, which was manufactured in Kazakhstan by AtyrauNefteMash. It was lifted into place with a 4,000-tonne crawler crane and a second crane rated at 1,700 tonnes, and the operation took about five hours. AtyrauNefteMash is also manufacturing a quench column more than 50 metres high weighing about 700 tonnes, as well as a 145-tonne deaerator. In total, about 40 Kazakh companies are involved in the project, with contracts worth more than $1.2 billion already signed. Domestic contractors take part in design and installation and supply concrete, piles, pipes, transformers and steel structures.
Products and markets
The complex is to produce 15 to 24 grades of polyethylene. About 40% of the volume will be premium grades used for pipes, cables, medical products, packaging, fibres and other goods. According to management estimates, at least 250,000 tonnes a year could be supplied to consumers in Kazakhstan. The remaining volumes are to be exported, with Europe, Turkey, CIS countries and Southeast Asia named as potential markets.
Jobs and training
More than a thousand permanent jobs are planned once the complex is in operation. International contractors Tecnicas Reunidas and Tecnimont have organised training programmes in Spain and Italy. A first group of 31 graduates completed the Tecnicas Reunidas programme, 22 of whom received job offers, and another 31 specialists are continuing their training. Under the MAIRE programme, 20 students of the Safi Utebayev Atyrau University of Oil and Gas have completed training, and more than 400 young people from Kazakhstan are to complete such training over four years. According to Kozyrev, more than 90% of the operations team are from Kazakhstan.
Project: Atyrau polyethylene complex · Kazakhstan · Under construction · $7.7 bn
Key facts
- Overall completion: more than 42%
- Capacity: 1.25 million tonnes of polyethylene per year
- First granules planned for July 2029
- Feedstock: up to 1.6 million tonnes of ethane a year from Tengiz field gas
- About 40 Kazakh companies, contracts worth more than $1.2 billion
- On site: more than 5,200 workers, peaking at over 15,000
- At least 250,000 tonnes a year for the Kazakh market
- More than a thousand permanent jobs after commissioning