Kazakhstan: Shift to Singaporean and Chinese Partners for Power Plant Construction

Investors, volumes and stages of the region's major projects – for European suppliers

· 3 Sources

Scroll
Energy Kazakhstan3 Sources

Published · last updated · 7 Apr 2026

Kazakhstan has excluded Russian companies from the construction of three combined heat and power plants. The projects in Kokshetau, Semey, and Ust-Kamenogorsk will now be implemented with Singaporean consortia and domestic firms. The shift follows the failure of Russian financing commitments.

New Contract Partners and Project Structure

Kazakhstan has ended cooperation with Russian companies on the construction of combined heat and power plants in Semey, Kokshetau, and Ust-Kamenogorsk. Instead, the projects will be implemented with domestic and Singaporean partners. The Kokshetau plant will be built entirely domestically, while the facilities in Semey and Ust-Kamenogorsk will be constructed by a Kazakhstan-Singapore consortium. EPC contracts for the two consortium projects were signed on January 30, 2026.

Schedule and Technical Equipment

Preliminary works, including engineering and geological surveys, begin in April 2026. The order for main equipment is expected in May 2026, with deliveries starting in the third quarter of 2027. Commissioning is scheduled for December 2029 (Semey, Ust-Kamenogorsk) and February 2029 (Kokshetau). All three plants use modern Chinese technology meeting environmental standards and incorporate AI systems for fault detection.

Costs and Background of the Change

The cost for the Kokshetau project is ₸355.6 billion (approx. $760 million), for Semey ₸578 billion (approx. $1.23 billion), and for Ust-Kamenogorsk ₸602 billion (approx. $1.28 billion). Originally, cooperation with Russia was planned, involving concessional loans from Russian banks. Since these financing commitments did not materialize, Kazakhstan decided to diversify its partners.

Project: Combined heat and power plants in Kokshetau, Semey, and Ust-Kamenogorsk · Kazakhstan · Under construction · $3.3 bn

Key facts

  • Start of preparatory works: April 2026
  • Cost Kokshetau: ₸355.6 billion
  • Cost Semey: ₸578 billion
  • Cost Ust-Kamenogorsk: ₸602 billion
  • Commissioning: February/December 2029
  • Technology provider: China (Harbin Electric International)

All sources (3)

  1. Kazakhstan Drops Russian Companies From Power Plant Projects, Signs Deal With SingaporeUNITED24 Media · · EN
  2. Kazakhstan Drops Russian Partners in Power Plant ProjectsThe Moscow Times · · EN
  3. Kazakhstan drops Russian firms from major power plant projectsThe New Voice of Ukraine · · EN

Imprint | Information pursuant to § 5 DDG

Company

AETEK GmbH Lindenstraße 5
63808 Haibach, Germany

Managing Director

Artur R. Pamin

Commercial Register

Amtsgericht Aschaffenburg
HRB 14157

VAT ID No.

DE288091462

EORI No.

DE644795536634916

Scan · LinkedIn