Kazakh Prime Minister Olzhas Bektenov has instructed the Ministry of Energy to complete the construction of gas processing plants (GPP) in Kashagan and Zhanaozen by the end of 2026 and early 2027, respectively. The projects have faced multiple delays. QazaqGaz and KazMunayGas are the responsible companies.
Order for Completion
Kazakh Prime Minister Olzhas Bektenov has instructed the Ministry of Energy to immediately complete the construction of major gas industry infrastructure projects, including the GPPs in Kashagan and Zhanaozen, as well as the second pipeline string of the 'Beineu–Bozoi–Shymkent' line. Strategic priority lies on coordination and control to increase gas availability.
Timeline and Capacities Kashagan
Completion of the Kashagan GPP is scheduled for 2026. The facility will have a capacity of 1 billion cubic meters per year. QazaqGaz is responsible for implementation. The cost for this first GPP is estimated at $1 billion. A second GPP with 2.5 billion cubic meters capacity is planned for 2028–2029, with estimated costs of $2–2.5 billion.
Zhanaozen Site and History
The new Zhanaozen GPP, implemented by KazMunayGas, is scheduled to commission in February 2027. The existing GPP from 1973 is over 90% worn out. The new complex will process up to 900 million cubic meters of gas annually, producing dry gas, LPG, pentane-hexane fraction, and sulfur. Commissioning was previously delayed from 2024 to 2025 and now to 2027.
Project: Kashagan Gas Processing Plant · Kazakhstan · Agreed · $2.5 bn
Key facts
- Completion GPP Kashagan: End of 2026
- Completion GPP Zhanaozen: February 2027
- Capacity GPP Kashagan (1st plant): 1 billion cubic meters/year
- Cost GPP Kashagan (1st plant): $1 billion
- Wear of existing GPP Zhanaozen: over 90%