According to the press service of KazMunayGas (KMG), more than 65 percent of the long-lead equipment for the new gas processing plant in Zhanaozen is ready. The plant is to process 900 million cubic metres of natural and associated gas per year and is being built using a modular method: the main process units are manufactured in factories and delivered to the site for assembly.
The plant is to produce sales gas and liquefied petroleum gas as well as a pentane-hexane fraction and supply gas products to the population and industrial enterprises of the Mangystau region. Of 240 long-lead equipment items, 169 are ready and 71 are in progress; overall manufacturing progress has reached 65.1 percent. Manufacturing of the main process units and assembly of modules continue at production sites in China.
Equipment is being delivered to Kazakhstan in stages. A first ship was unloaded at the port of Ersai, carrying a flare unit, a thermal oxidiser, an oil heating furnace, heat exchangers and tanks with electric heaters. A second ship delivered steel structures for the pipe racks of the plant's inter-unit utilities. Two more ships are en route; one of them carries the plant's key equipment: two Siemens compressor units and two gas turbines.
At the site, earthworks, foundation work and the assembly of spherical and cylindrical tanks are under way. So far 20,970 cubic metres of concrete have been placed, 33.3 percent of the planned volume. According to KMG, the resources deployed are being increased step by step as the work front expands.
Project: Zhanaozen gas processing plant · Kazakhstan · Under construction
Key facts
- Capacity: 900 million cubic metres of natural and associated gas per year
- Long-lead equipment: 169 of 240 items ready, 71 in progress (65.1 percent)
- Concrete: 20,970 cubic metres placed, 33.3 percent of the planned volume
- Key equipment en route: two Siemens compressor units and two gas turbines
- Source: press service of KazMunayGas (KMG)